Key facts

Capacity
1.5 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
September 1981First generator online
Operator
Haw River Hydro CoEIA operator ID 4980
Grid
DUKBalancing authority DUK
Price nodes
None linkedNo verified ISO node
Location
Alamance County, NC35.9483, −79.3244
EIA plant ID
10258EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Haw River Hydro produces

Free · EIA-923

Net generation, 2025

3.53 GWh

3,533 MWh, final

Capacity factor, 2025

26.9%

2024: 31.5%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

3.0–8.8

GWh a year. Low 2023, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
20014Not reported12 of 12
20024Not reported12 of 12
20035Not reported12 of 12
20045,602Not reported12 of 12
20056Not reported12 of 12
20065Not reported12 of 12
20074Not reported12 of 12
20084,000Not reported12 of 12
20095,662Not reported12 of 12
20105,47041.6%12 of 12
20115,35440.7%12 of 12
20124,90537.2%12 of 12
20136,90452.5%12 of 12
20145,36840.9%12 of 12
20155,81144.2%12 of 12
20166,02545.7%12 of 12
20174,12331.4%12 of 12
20186,73651.3%12 of 12
20197,05953.7%12 of 12
20208,81166.9%12 of 12
20215,38040.9%12 of 12
20224,20332.0%12 of 12
20233,04323.2%12 of 12
20244,14431.5%12 of 12
20253,53326.9%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric1.0September 1981
2Conventional Hydroelectric0.5June 1982

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Haw River Hydro Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Haw River Hydro and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Haw River Hydro

Questions about Haw River Hydro

How much power does Haw River Hydro produce?

Haw River Hydro reported 3,533 MWh (3.53 GWh) of net generation in 2025, a 26.9% capacity factor on 1.5 MW of nameplate capacity.

Where is Haw River Hydro?

Haw River Hydro is in Alamance County, North Carolina, at 35.9483, −79.3244. It is in the Duke Energy Carolinas balancing area (DUK).

Who operates Haw River Hydro?

EIA-860M for August 2026 lists Haw River Hydro Co as the operator (EIA operator ID 4980). The operator is not always the owner.

When did Haw River Hydro start operating?

Its first generator began operating in September 1981, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page