Wood biomassOperatingPJM

Altavista Power Station

Wood biomass power plant in Campbell County, Virginia. 71.1 MW of nameplate capacity across 1 generator, operated by Virginia Electric & Power Co.

Also known as EIA plant 10773

Analyst: free account, 1 question a day.

Altavista SolarHCE Roark Mill Solar, LLCLeesvilleSycamore SolarWhitehorn SolarDepot Solar Center, LLCAltavista10 km
Open in the map
6 plants within 22 km, from EIA coordinates.

Key facts

Capacity
71.1 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
February 1992First generator online
Operator
Virginia Electric & Power CoEIA operator ID 19876
Grid
PJMBalancing authority PJM
Price nodes
1 PJM nodeResource nodes with prices
Location
Campbell County, VA37.1187, −79.2736
EIA plant ID
10773EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Altavista produces

Free · EIA-923

Net generation, 2025

300 GWh

299,825 MWh, final

Capacity factor, 2025

48.1%

2024: 43.0%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2017 to 2025

268.7–334.1

GWh a year. Low 2024, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000323,033Not reported12 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003403,069Not reported12 of 12
2004327,597Not reported12 of 12
2005348,093Not reported12 of 12
2006348,197Not reported12 of 12
2007397,814Not reported12 of 12
2008185,557Not reported12 of 12
2009129,685Not reported12 of 12
2010161,61025.9%12 of 12
2011Not reportedNot reported0 of 12
201200.0%11 of 12
2013Not reportedNot reported0 of 12
201455,97936.9%3 of 12
201574,87647.2%3 of 12
201652,28751.1%2 of 12
2017275,60344.2%12 of 12
2018274,06944.0%12 of 12
2019272,45743.7%12 of 12
2020297,90347.7%12 of 12
2021322,80951.8%12 of 12
2022334,10353.6%12 of 12
2023283,17045.5%12 of 12
2024268,68643.0%12 of 12
2025299,82548.1%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · PJM

Emissions

Free · EPA CAMPD

CO₂, 2025

500,107

US short tons. 2024: 429,856

SO₂, 2025

13

US short tons

NOx, 2025

273

US short tons

CO₂ per MWh, calculated

1.67 t

About 3,336 lb per MWh

2 of 2 EPA units reported CO₂ in 2025 (1, 2), matched to EIA plant 10773 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Wood/Wood Waste Biomass71.1February 1992

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Virginia Electric & Power Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Altavista Power Station and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Altavista

More plants operated by Virginia Electric & Power Co

Questions about Altavista

How much power does Altavista Power Station produce?

Altavista Power Station reported 299,825 MWh (300 GWh) of net generation in 2025, a 48.1% capacity factor on 71.1 MW of nameplate capacity.

Where is Altavista Power Station?

Altavista Power Station is in Campbell County, Virginia, at 37.1187, −79.2736. It is in the PJM Interconnection, LLC balancing area (PJM).

Who operates Altavista Power Station?

EIA-860M for August 2026 lists Virginia Electric & Power Co as the operator (EIA operator ID 19876). The operator is not always the owner.

When did Altavista Power Station start operating?

Its first generator began operating in February 1992, according to EIA-860M.

Does InfraMap have power prices for Altavista Power Station?

Yes. InfraMap has PJM day-ahead and real-time prices at 1 price node linked to Altavista Power Station, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • PJM day-ahead and real-time prices; node and hub assignments as of 2026-10-05