Natural gasOperatingMISO

Archer Daniels Midland Peoria

Natural gas power plant in Peoria County, Illinois. 18 MW of nameplate capacity across 1 generator, operated by BioUrja Renewables LLC.

Also known as EIA plant 10866

Analyst: free account, 1 question a day.

Tazewell Gas RecoveryPeoria County IL S2SCS Galena 012589 Peoria, LLC5 km
Open in the map
6 plants within 12 km, from EIA coordinates.

Key facts

Capacity
18 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
January 1988First generator online
Operator
BioUrja Renewables LLCEIA operator ID 64580
Grid
MISOBalancing authority MISO
Price nodes
None linkedNo verified ISO node
Location
Peoria County, IL40.6772, −89.6049
EIA plant ID
10866EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Archer Daniels Midland Peoria produces

Free · EIA-923

Net generation, 2025

72.9 GWh

72,914 MWh, final

Capacity factor, 2025

46.2%

2024: 49.8%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

23.4–202.7

GWh a year. Low 2023, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000317,544Not reported12 of 12
2001266,092Not reported12 of 12
2002282,404Not reported12 of 12
20030Not reported12 of 12
2004283,396Not reported12 of 12
2005268,592Not reported12 of 12
2006200,932Not reported12 of 12
2007260,047Not reported12 of 12
2008252,649Not reported12 of 12
2009224,218Not reported12 of 12
2010239,18442.7%12 of 12
2011235,66542.0%12 of 12
2012151,08126.9%12 of 12
2013166,857Not reported12 of 12
2014189,00759.9%12 of 12
2015190,89060.5%12 of 12
2016202,72764.1%12 of 12
2017192,56761.1%12 of 12
2018184,15458.4%12 of 12
201983,75426.6%12 of 12
202071,54822.6%12 of 12
202150,55416.0%12 of 12
202243,02913.6%12 of 12
202323,3627.4%12 of 12
202478,66649.8%12 of 12
202572,91446.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN7Natural Gas Fired Combustion Turbine18.0January 1988

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists BioUrja Renewables LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Archer Daniels Midland Peoria and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Archer Daniels Midland Peoria

Questions about Archer Daniels Midland Peoria

How much power does Archer Daniels Midland Peoria produce?

Archer Daniels Midland Peoria reported 72,914 MWh (72.9 GWh) of net generation in 2025, a 46.2% capacity factor on 18 MW of nameplate capacity.

Where is Archer Daniels Midland Peoria?

Archer Daniels Midland Peoria is in Peoria County, Illinois, at 40.6772, −89.6049. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Archer Daniels Midland Peoria?

EIA-860M for August 2026 lists BioUrja Renewables LLC as the operator (EIA operator ID 64580). The operator is not always the owner.

When did Archer Daniels Midland Peoria start operating?

Its first generator began operating in January 1988, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page