Key facts

Capacity
21.3 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
April 1972First generator online
Operator
City of Webster City - (IA)EIA operator ID 20259
Grid
MISOBalancing authority MISO
Price nodes
1 SPP nodeResource nodes with prices
Location
Hamilton County, IA42.4710, −93.8150
EIA plant ID
1198EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Webster City produces

Free · EIA-923

Net generation, 2025

383 MWh

383 MWh, final

Capacity factor, 2025

0.2%

2024: 0.4%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

0.1–3.4

GWh a year. Low 2020, high 2021

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20000Not reported12 of 12
2001Not reportedNot reported0 of 12
2002232Not reported12 of 12
2003422Not reported12 of 12
200485Not reported12 of 12
200564Not reported12 of 12
200650Not reported12 of 12
200741Not reported12 of 12
2008140Not reported12 of 12
200934Not reported12 of 12
2010440.0%12 of 12
2011270.0%12 of 12
2012510.0%12 of 12
2013310.0%12 of 12
2014350.0%12 of 12
20152290.1%12 of 12
20164220.2%12 of 12
2017680.0%12 of 12
20182030.1%12 of 12
20196570.4%12 of 12
2020560.0%12 of 12
20213,3721.8%12 of 12
20221,4900.8%12 of 12
20232,0381.1%12 of 12
20248090.4%12 of 12
20253830.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · SPP

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
6Petroleum Liquids21.3April 1972

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists City of Webster City - (IA) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Webster City and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Webster City

Questions about Webster City

How much power does Webster City produce?

Webster City reported 383 MWh (383 MWh) of net generation in 2025, a 0.2% capacity factor on 21.3 MW of nameplate capacity.

Where is Webster City?

Webster City is in Hamilton County, Iowa, at 42.4710, −93.8150. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Webster City?

EIA-860M for August 2026 lists City of Webster City - (IA) as the operator (EIA operator ID 20259). The operator is not always the owner.

When did Webster City start operating?

Its first generator began operating in April 1972, according to EIA-860M.

Does InfraMap have power prices for Webster City?

Yes. InfraMap has SPP day-ahead and real-time prices at 1 price node linked to Webster City, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • SPP day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page