Natural gasOilOperatingSPP

Belleville

Natural gas and oil power plant in Republic County, Kansas. 9.4 MW of nameplate capacity across 4 generators, operated by City of Belleville - (KS).

Also known as Belleville Power Plant · EIA plant 1263

Analyst: free account, 1 question a day.

High Banks WindDeshler SolarDeshlerCliftonHebronCity of SuperiorBelleville25 km
Open in the map
6 plants within 41 km, from EIA coordinates.

Key facts

Capacity
9.4 MWNatural gas 6.4 · Oil 3.0
Generators
4 operatingEIA-860M, August 2026
Operating since
January 1955First generator online
Operator
City of Belleville - (KS)EIA operator ID 1512
Grid
SPPBalancing authority SWPP
Price nodes
None linkedNo verified ISO node
Location
Republic County, KS39.8328, −97.6320
EIA plant ID
1263EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Belleville produces

Free · EIA-923

Net generation, 2025

513 MWh

513 MWh, final

Capacity factor, 2025

Not reported

2024: 0.2%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

−255.0–513.0

MWh a year. Low 2019, high 2025

Annual net generation, MWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20000Not reported12 of 12
20012,555Not reported12 of 12
2002972Not reported12 of 12
2003398Not reported12 of 12
200448Not reported12 of 12
2005180Not reported12 of 12
2006632Not reported12 of 12
2007994Not reported12 of 12
2008544Not reported12 of 12
2009524Not reported12 of 12
20102690.2%12 of 12
20111840.1%12 of 12
20121850.1%12 of 12
20132560.2%12 of 12
20143050.2%12 of 12
20151180.1%12 of 12
20161770.1%12 of 12
20171770.1%12 of 12
20181050.1%12 of 12
2019−255-0.2%12 of 12
2020155Not reported12 of 12
20212770.2%12 of 12
20223270.3%12 of 12
20231780.1%12 of 12
20242050.2%12 of 12
2025513Not reported12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
4Natural Gas Internal Combustion Engine1.0January 1955
5Natural Gas Internal Combustion Engine1.7January 1961
6Natural Gas Internal Combustion Engine3.7January 1966
8Petroleum Liquids3.0January 2005

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists City of Belleville - (KS) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Belleville and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Belleville

Questions about Belleville

How much power does Belleville produce?

Belleville reported 513 MWh (513 MWh) of net generation in 2025.

Where is Belleville?

Belleville is in Republic County, Kansas, at 39.8328, −97.6320. It is in the Southwest Power Pool balancing area (SWPP).

Who operates Belleville?

EIA-860M for August 2026 lists City of Belleville - (KS) as the operator (EIA operator ID 1512). The operator is not always the owner.

Is Belleville a natural gas or a oil plant?

Both. Natural gas capacity totals 6.4 MW and oil capacity totals 3 MW.

When did Belleville start operating?

Its first generator began operating in January 1955, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page