HydroOperatingMISO

Croton

Hydro power plant in Newaygo County, Michigan. 8.9 MW of nameplate capacity across 4 generators, operated by Consumers Energy Co - (MI).

Also known as Croton Hydroelectric Plant · EIA plant 1701

Analyst: free account, 1 question a day.

HardyCentral GeneratingHazel Solar, LLCRogersCroton10 km
Open in the map
5 plants within 25 km, from EIA coordinates.

Key facts

Capacity
8.9 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
January 1907First generator online
Operator
Consumers Energy Co - (MI)EIA operator ID 4254
Grid
MISOBalancing authority MISO
Price nodes
1 MISO nodeResource nodes with prices
Location
Newaygo County, MI43.4373, −85.6645
EIA plant ID
1701EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Croton produces

Free · EIA-923

Net generation, 2025

29.5 GWh

29,497 MWh, final

Capacity factor, 2025

37.8%

2024: 37.2%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

20.4–39.8

GWh a year. Low 2023, high 2019

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
200033,083Not reported12 of 12
200142,550Not reported12 of 12
200237,270Not reported12 of 12
200330,364Not reported12 of 12
200442,938Not reported12 of 12
200537,635Not reported12 of 12
200647,689Not reported12 of 12
200737,980Not reported12 of 12
200840,762Not reported12 of 12
200943,085Not reported12 of 12
201030,94939.7%12 of 12
201138,80649.8%12 of 12
201233,54042.9%12 of 12
201326,23033.6%12 of 12
201425,96433.3%12 of 12
201537,50248.1%12 of 12
201637,93748.5%12 of 12
201733,95743.6%12 of 12
201835,26645.2%12 of 12
201939,84651.1%12 of 12
202026,36833.7%12 of 12
202131,29440.1%12 of 12
202228,62836.7%12 of 12
202320,38026.1%12 of 12
202429,11537.2%12 of 12
202529,49737.8%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric3.0January 1907
2Conventional Hydroelectric3.0January 1907
3Conventional Hydroelectric1.4January 1915
4Conventional Hydroelectric1.5January 1912

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Consumers Energy Co - (MI) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Croton and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Croton

More plants operated by Consumers Energy Co - (MI)

Questions about Croton

How much power does Croton produce?

Croton reported 29,497 MWh (29.5 GWh) of net generation in 2025, a 37.8% capacity factor on 8.9 MW of nameplate capacity.

Where is Croton?

Croton is in Newaygo County, Michigan, at 43.4373, −85.6645. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Croton?

EIA-860M for August 2026 lists Consumers Energy Co - (MI) as the operator (EIA operator ID 4254). The operator is not always the owner.

When did Croton start operating?

Its first generator began operating in January 1907, according to EIA-860M.

Does InfraMap have power prices for Croton?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Croton, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page