Key facts

Capacity
2 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
May 2005First generator online
Operator
Adrian Public Utilities CommEIA operator ID 150
Grid
SPPBalancing authority SWPP
Price nodes
1 MISO nodeResource nodes with prices
Location
Nobles County, MN43.6371, −95.9328
EIA plant ID
1956EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Adrian produces

Free · EIA-923

Net generation, 2025

12 MWh

12 MWh, final

Capacity factor, 2025

0.1%

2024: 0.1%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

7.0–91.0

MWh a year. Low 2023, high 2019

Annual net generation, MWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20000Not reported12 of 12
2001Not reportedNot reported0 of 12
20020Not reported12 of 12
20030Not reported12 of 12
20042Not reported12 of 12
200543Not reported12 of 12
20069Not reported12 of 12
200734Not reported12 of 12
200814Not reported12 of 12
20098Not reported12 of 12
2010180.1%12 of 12
201180.0%12 of 12
2012100.1%12 of 12
2013870.5%12 of 12
2014380.2%12 of 12
2015240.1%12 of 12
201680.0%12 of 12
2017200.1%12 of 12
2018130.1%12 of 12
2019910.5%12 of 12
2020120.1%12 of 12
2021170.1%12 of 12
2022210.1%12 of 12
202370.0%12 of 12
2024210.1%12 of 12
2025120.1%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
5Petroleum Liquids2.0May 2005

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Adrian Public Utilities Comm as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Adrian and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Adrian

Questions about Adrian

How much power does Adrian produce?

Adrian reported 12 MWh (12 MWh) of net generation in 2025, a 0.1% capacity factor on 2 MW of nameplate capacity.

Where is Adrian?

Adrian is in Nobles County, Minnesota, at 43.6371, −95.9328. It is in the Southwest Power Pool balancing area (SWPP).

Who operates Adrian?

EIA-860M for August 2026 lists Adrian Public Utilities Comm as the operator (EIA operator ID 150). The operator is not always the owner.

When did Adrian start operating?

Its first generator began operating in May 2005, according to EIA-860M.

Does InfraMap have power prices for Adrian?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Adrian, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05