Natural gasOperatingSPP

Horseshoe Lake

Natural gas power plant in Oklahoma County, Oklahoma. 564 MW of nameplate capacity across 3 generators, operated by Oklahoma Gas & Electric Co.

Also known as Horseshoe Lake Power Plant · EIA plant 2951

Analyst: free account, 1 question a day.

Redbud Power PlantTinkerNorman SolarFrontierMcClain Energy FacilityHorseshoe Lake25 km
Open in the map
6 plants within 44 km, from EIA coordinates.

Key facts

Capacity
564 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
June 1969First generator online
Operator
Oklahoma Gas & Electric CoEIA operator ID 14063
Grid
SPPBalancing authority SWPP
Price nodes
2 SPP nodesResource nodes with prices
Location
Oklahoma County, OK35.5087, −97.1797
EIA plant ID
2951EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Horseshoe Lake produces

Free · EIA-923

Net generation, 2025

Not reported

Not reported MWh, final. 0 of 12 months reported

Capacity factor, 2025

Not reported

2024: Not reported

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20001,003,977Not reported12 of 12
20011,072,349Not reported12 of 12
20021,289,533Not reported12 of 12
2003884,566Not reported11 of 12
2004995,992Not reported12 of 12
2005698,429Not reported12 of 12
20061,008,116Not reported12 of 12
20071,115,379Not reported12 of 12
2008903,434Not reported12 of 12
2009877,931Not reported12 of 12
20101,641,38119.2%12 of 12
20111,010,24511.8%12 of 12
20121,073,82312.6%12 of 12
2013746,348Not reported12 of 12
201425,8573.6%1 of 12
2015Not reportedNot reported0 of 12
2016717,0068.4%12 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
2024Not reportedNot reported0 of 12
2025Not reportedNot reported0 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · SPP

Emissions

Free · EPA CAMPD

CO₂, 2025

311,066

US short tons. 2024: Not reported

SO₂, 2025

2

US short tons

NOx, 2025

457

US short tons

3 of 3 EPA units reported CO₂ in 2025 (10, 6, 7, 8, 9), matched to EIA plant 2951 through the EPA–EIA crosswalk.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

995

million gallons

Consumption, 2024

1,719

million gallons

Source

Settling Basin Pond; Horseshoe Lake

Surface, Fresh. Induced-draft tower

Watershed stress

High · 0.643

USGS SUI, HUC12 Horseshoe Lake-North Canadian River

24 of 24 cooling months report withdrawal. SUI of the HUC12 containing the plant. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
8Natural Gas Steam Turbine443.0June 1969
9Natural Gas Fired Combustion Turbine60.5June 2001
10Natural Gas Fired Combustion Turbine60.5June 2001

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Oklahoma Gas & Electric Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Horseshoe Lake and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Horseshoe Lake

More plants operated by Oklahoma Gas & Electric Co

Questions about Horseshoe Lake

Where is Horseshoe Lake?

Horseshoe Lake is in Oklahoma County, Oklahoma, at 35.5087, −97.1797. It is in the Southwest Power Pool balancing area (SWPP).

Who operates Horseshoe Lake?

EIA-860M for August 2026 lists Oklahoma Gas & Electric Co as the operator (EIA operator ID 14063). The operator is not always the owner.

When did Horseshoe Lake start operating?

Its first generator began operating in June 1969, according to EIA-860M.

Does InfraMap have power prices for Horseshoe Lake?

Yes. InfraMap has SPP day-ahead and real-time prices at 2 price nodes linked to Horseshoe Lake, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • SPP day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page