Key facts

Capacity
4 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
January 1936First generator online
Operator
Great Bay Hydro CorpEIA operator ID 49852
Grid
ISO-NEBalancing authority ISNE
Price nodes
1 ISONE nodeResource nodes with prices
Location
Orleans County, VT44.9376, −72.1800
EIA plant ID
3731EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Newport produces

Free · EIA-923

Net generation, 2025

12.9 GWh

12,929 MWh, final

Capacity factor, 2025

36.9%

2024: 58.8%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

8.6–20.6

GWh a year. Low 2021, high 2024

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20000Not reported12 of 12
200111,682Not reported12 of 12
200213,187Not reported12 of 12
20030Not reported12 of 12
200412,714Not reported12 of 12
200515,678Not reported12 of 12
200621,719Not reported12 of 12
200719,006Not reported12 of 12
200818,876Not reported12 of 12
200917,694Not reported12 of 12
201018,00651.4%12 of 12
201119,07354.4%12 of 12
201213,14837.4%12 of 12
201317,64450.4%12 of 12
201415,58644.5%12 of 12
201516,09545.9%12 of 12
201614,29540.7%12 of 12
201716,95948.4%12 of 12
201815,06443.0%12 of 12
201917,81150.8%12 of 12
202015,41343.9%12 of 12
20218,61824.6%12 of 12
202215,29443.6%12 of 12
202319,81856.6%12 of 12
202420,64558.8%12 of 12
202512,92936.9%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ISONE

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric1.7January 1940
2Conventional Hydroelectric1.7January 1944
3Conventional Hydroelectric0.6January 1936

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Great Bay Hydro Corp as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Newport and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Newport

Questions about Newport

How much power does Newport produce?

Newport reported 12,929 MWh (12.9 GWh) of net generation in 2025, a 36.9% capacity factor on 4 MW of nameplate capacity.

Where is Newport?

Newport is in Orleans County, Vermont, at 44.9376, −72.1800. It is in the ISO New England Inc. balancing area (ISNE).

Who operates Newport?

EIA-860M for August 2026 lists Great Bay Hydro Corp as the operator (EIA operator ID 49852). The operator is not always the owner.

When did Newport start operating?

Its first generator began operating in January 1936, according to EIA-860M.

Does InfraMap have power prices for Newport?

Yes. InfraMap has ISONE day-ahead and real-time prices at 1 price node linked to Newport, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ISONE day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page