Key facts

Capacity
1.6 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
August 1914First generator online
Operator
Village of Morrisville - (VT)EIA operator ID 12989
Grid
ISO-NEBalancing authority ISNE
Price nodes
1 ISONE nodeResource nodes with prices
Location
Lamoille County, VT44.5776, −72.6119
EIA plant ID
3765EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Cadys Falls produces

Free · EIA-923

Net generation, 2025

2.21 GWh

2,208 MWh, final

Capacity factor, 2025

15.8%

2024: 1.0%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

0.0–2.7

GWh a year. Low 2023, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20000Not reported12 of 12
20012,745Not reported12 of 12
20024,233Not reported12 of 12
20032,505Not reported12 of 12
20043,297Not reported12 of 12
20052,984Not reported12 of 12
20063,082Not reported12 of 12
20071,981Not reported12 of 12
20084,047Not reported12 of 12
20093,029Not reported12 of 12
20102,74219.6%12 of 12
20111,0757.7%12 of 12
20121,0757.6%12 of 12
20133,91127.9%12 of 12
20143,15522.5%12 of 12
20152,66719.0%12 of 12
20162,33616.6%12 of 12
20172,14415.3%12 of 12
20181,40310.0%12 of 12
20191,92313.7%12 of 12
20201,80612.9%12 of 12
20211,1328.1%12 of 12
20224273.0%12 of 12
2023100.1%12 of 12
20241391.0%12 of 12
20252,20815.8%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ISONE

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric0.8August 1914
2Conventional Hydroelectric0.8August 1947

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Village of Morrisville - (VT) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Cadys Falls and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Cadys Falls

More plants operated by Village of Morrisville - (VT)

Questions about Cadys Falls

How much power does Cadys Falls produce?

Cadys Falls reported 2,208 MWh (2.21 GWh) of net generation in 2025, a 15.8% capacity factor on 1.6 MW of nameplate capacity.

Where is Cadys Falls?

Cadys Falls is in Lamoille County, Vermont, at 44.5776, −72.6119. It is in the ISO New England Inc. balancing area (ISNE).

Who operates Cadys Falls?

EIA-860M for August 2026 lists Village of Morrisville - (VT) as the operator (EIA operator ID 12989). The operator is not always the owner.

When did Cadys Falls start operating?

Its first generator began operating in August 1914, according to EIA-860M.

Does InfraMap have power prices for Cadys Falls?

Yes. InfraMap has ISONE day-ahead and real-time prices at 1 price node linked to Cadys Falls, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ISONE day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page