Natural gasOperatingERCOT

Corpus Christi

Natural gas power plant in Nueces County, Texas. 41 MW of nameplate capacity across 1 generator, operated by Equistar Chemicals LP.

Also known as EIA plant 50475

Analyst: free account, 1 question a day.

Regis HearnCarinaCorpus RefineryWeil Tract BESSAggreko MSR Grid PC2Corpus Christi5 km
Open in the map
6 plants within 13 km, from EIA coordinates.

Key facts

Capacity
41 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
May 1989First generator online
Operator
Equistar Chemicals LPEIA operator ID 5065
Grid
ERCOTBalancing authority ERCO
Price nodes
1 ERCOT nodeResource nodes with prices
Location
Nueces County, TX27.8111, −97.5958
EIA plant ID
50475EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Corpus Christi produces

Free · EIA-923

Net generation, 2025

85.6 GWh

85,583 MWh, final

Capacity factor, 2025

23.8%

2024: 15.2%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

54.6–96.5

GWh a year. Low 2024, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001303,019Not reported12 of 12
2002280,414Not reported12 of 12
2003Not reportedNot reported0 of 12
2004241,182Not reported12 of 12
2005232,185Not reported12 of 12
2006281,285Not reported12 of 12
2007273,504Not reported12 of 12
2008297,206Not reported12 of 12
2009277,764Not reported12 of 12
201093,17825.9%12 of 12
2011105,63729.4%12 of 12
2012112,64431.3%12 of 12
2013106,08529.5%12 of 12
201496,02926.7%12 of 12
201580,42322.4%12 of 12
201657,44616.0%12 of 12
201779,36022.1%12 of 12
201867,40318.8%12 of 12
201976,45121.3%12 of 12
202096,51226.8%12 of 12
202173,32920.4%12 of 12
202268,76619.1%12 of 12
202372,90720.3%12 of 12
202454,63115.2%12 of 12
202585,58323.8%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Natural Gas Fired Combustion Turbine41.0May 1989

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Equistar Chemicals LP as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Corpus Christi and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Corpus Christi

More plants operated by Equistar Chemicals LP

Questions about Corpus Christi

How much power does Corpus Christi produce?

Corpus Christi reported 85,583 MWh (85.6 GWh) of net generation in 2025, a 23.8% capacity factor on 41 MW of nameplate capacity.

Where is Corpus Christi?

Corpus Christi is in Nueces County, Texas, at 27.8111, −97.5958. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Corpus Christi?

EIA-860M for August 2026 lists Equistar Chemicals LP as the operator (EIA operator ID 5065). The operator is not always the owner.

When did Corpus Christi start operating?

Its first generator began operating in May 1989, according to EIA-860M.

Does InfraMap have power prices for Corpus Christi?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Corpus Christi, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page