Petroleum cokeOperatingNWMT

Yellowstone Energy LP

Petroleum coke power plant in Yellowstone County, Montana. 68 MW of nameplate capacity across 1 generator, operated by Yellowstone Energy LP.

Also known as Yellowstone Energy · EIA plant 50931

Analyst: free account, 1 question a day.

Western Sugar Coopera…MTSUNYellowstone County Generating StationTwo Dot Wind Broadview East LLCYellowstone Energy LP25 km
Open in the map
4 plants within 44 km, from EIA coordinates.

Key facts

Capacity
68 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
June 1995First generator online
Operator
Yellowstone Energy LPEIA operator ID 21773
Grid
NWMTBalancing authority NWMT
Price nodes
None linkedNo verified ISO node
Location
Yellowstone County, MT45.8117, −108.4278
EIA plant ID
50931EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Yellowstone Energy LP produces

Free · EIA-923

Net generation, 2025

458 GWh

458,357 MWh, final

Capacity factor, 2025

76.9%

2024: 63.9%

January to July 2026

218 GWh

Provisional

Range, 2015 to 2025

381.8–500.1

GWh a year. Low 2024, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000441,280Not reported12 of 12
2001425,959Not reported12 of 12
2002348,123Not reported12 of 12
2003378,065Not reported12 of 12
2004433,670Not reported12 of 12
2005412,466Not reported12 of 12
2006408,031Not reported12 of 12
2007481,724Not reported12 of 12
2008404,942Not reported12 of 12
2009479,335Not reported12 of 12
2010397,52769.8%12 of 12
2011444,29278.0%12 of 12
2012454,794Not reported12 of 12
2013448,66875.3%12 of 12
2014404,66067.9%12 of 12
2015500,08784.0%12 of 12
2016452,01475.7%12 of 12
2017459,44377.1%12 of 12
2018442,91074.4%12 of 12
2019459,71977.2%12 of 12
2020459,33976.9%12 of 12
2021454,27476.3%12 of 12
2022459,07877.1%12 of 12
2023490,76082.4%12 of 12
2024381,83263.9%12 of 12
2025458,35776.9%12 of 12
2026 (provisional, partial year)217,61262.9%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Petroleum Coke68.0June 1995

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Yellowstone Energy LP as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Yellowstone Energy LP and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Yellowstone Energy LP

Questions about Yellowstone Energy LP

How much power does Yellowstone Energy LP produce?

Yellowstone Energy LP reported 458,357 MWh (458 GWh) of net generation in 2025, a 76.9% capacity factor on 68 MW of nameplate capacity. From January to July 2026 it reported 218 GWh, which is provisional.

Where is Yellowstone Energy LP?

Yellowstone Energy LP is in Yellowstone County, Montana, at 45.8117, −108.4278. It is in the NorthWestern Energy (NWMT) balancing area (NWMT).

Who operates Yellowstone Energy LP?

EIA-860M for August 2026 lists Yellowstone Energy LP as the operator (EIA operator ID 21773). The operator is not always the owner.

When did Yellowstone Energy LP start operating?

Its first generator began operating in June 1995, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page