Natural gasOperatingERCOT

Oyster Creek Unit VIII

Natural gas power plant in Brazoria County, Texas. 497.9 MW of nameplate capacity across 4 generators, operated by Dow Chemical Company-Oyster Creek VIII.

Also known as EIA plant 54676

Analyst: free account, 1 question a day.

Freeport LP Pretreatm…PraxairOyster Creek Unit VIII2 km
Open in the map
5 plants within 6.5 km, from EIA coordinates.

Key facts

Capacity
497.9 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
October 1994First generator online
Operator
Dow Chemical Company-Oyster Creek VIIIEIA operator ID 5374
Grid
ERCOTBalancing authority ERCO
Price nodes
1 ERCOT nodeResource nodes with prices
Location
Brazoria County, TX28.9802, −95.3420
EIA plant ID
54676EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Oyster Creek Unit VIII produces

Free · EIA-923

Net generation, 2025

2.50 TWh

2,500,104 MWh, final

Capacity factor, 2025

57.3%

2024: 53.0%

January to July 2026

1.45 TWh

Provisional

Range, 2015 to 2025

2.2–2.8

TWh a year. Low 2015, high 2020

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20002,768,614Not reported12 of 12
20013,014,837Not reported12 of 12
20022,553,673Not reported12 of 12
20032,221,273Not reported12 of 12
20042,967,717Not reported12 of 12
20052,940,967Not reported12 of 12
20062,450,025Not reported12 of 12
20072,531,786Not reported12 of 12
20082,379,794Not reported12 of 12
20092,336,904Not reported12 of 12
20102,204,10050.5%12 of 12
20112,149,95149.3%12 of 12
20122,302,32452.6%12 of 12
20132,339,970Not reported12 of 12
20142,166,01949.7%12 of 12
20152,182,64650.0%12 of 12
20162,388,07154.6%12 of 12
20172,397,65655.0%12 of 12
20182,190,55450.2%12 of 12
20192,596,66059.5%12 of 12
20202,792,12763.8%12 of 12
20212,503,44257.4%12 of 12
20222,713,11162.2%12 of 12
20232,686,61861.6%12 of 12
20242,316,22453.0%12 of 12
20252,500,10457.3%12 of 12
2026 (provisional, partial year)1,452,28157.3%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

403

million gallons

Consumption, 2024

255

million gallons

Source

Brazos River (Dow Chemical)

Surface, Fresh. Induced-draft tower

Watershed stress

Low · 0.233

USGS SUI, HUC12 Lower Oyster Creek-Frontal Freeport Harbor Channel

12 of 12 cooling months report withdrawal. SUI of the HUC12 containing the plant. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
G81Natural Gas Fired Combined Cycle99.0October 1994
G82Natural Gas Fired Combined Cycle99.0October 1994
G83Natural Gas Fired Combined Cycle99.0October 1994
G84Natural Gas Fired Combined Cycle200.9October 1994

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Dow Chemical Company-Oyster Creek VIII as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Oyster Creek Unit VIII and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Oyster Creek Unit VIII

Questions about Oyster Creek Unit VIII

How much power does Oyster Creek Unit VIII produce?

Oyster Creek Unit VIII reported 2,500,104 MWh (2.50 TWh) of net generation in 2025, a 57.3% capacity factor on 497.9 MW of nameplate capacity. From January to July 2026 it reported 1.45 TWh, which is provisional.

Where is Oyster Creek Unit VIII?

Oyster Creek Unit VIII is in Brazoria County, Texas, at 28.9802, −95.3420. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Oyster Creek Unit VIII?

EIA-860M for August 2026 lists Dow Chemical Company-Oyster Creek VIII as the operator (EIA operator ID 5374). The operator is not always the owner.

When did Oyster Creek Unit VIII start operating?

Its first generator began operating in October 1994, according to EIA-860M.

Does InfraMap have power prices for Oyster Creek Unit VIII?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Oyster Creek Unit VIII, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page