Landfill gasOperatingPJM

I 95 Landfill Phase II

Landfill gas power plant in Fairfax County, Virginia. 3.2 MW of nameplate capacity across 4 generators, operated by NextEra Renewable Fuels, LLC.

Also known as EIA plant 54723

Analyst: free account, 1 question a day.

Covanta Alexandria/Arlington EnergyPossum PointChurch Street PlantRipleyI 95 Landfill Phase II10 km
Open in the map
6 plants within 21 km, from EIA coordinates.

Key facts

Capacity
3.2 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
March 1993First generator online
Operator
NextEra Renewable Fuels, LLCEIA operator ID 57249
Grid
PJMBalancing authority PJM
Price nodes
1 PJM nodeResource nodes with prices
Location
Fairfax County, VA38.6892, −77.2375
EIA plant ID
54723EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power I 95 Landfill Phase II produces

Free · EIA-923

Net generation, 2025

12.9 GWh

12,938 MWh, final

Capacity factor, 2025

46.2%

2024: 68.8%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

12.9–24.3

GWh a year. Low 2025, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
200125,284Not reported12 of 12
200225,526Not reported12 of 12
200323,080Not reported12 of 12
200425,094Not reported12 of 12
200524,975Not reported12 of 12
200625,392Not reported12 of 12
200725,627Not reported12 of 12
200825,419Not reported12 of 12
200925,875Not reported12 of 12
201026,68095.2%12 of 12
201126,27093.7%12 of 12
201225,12589.4%12 of 12
201316,97760.6%12 of 12
201411,35740.5%12 of 12
201513,05346.6%12 of 12
201617,42662.0%12 of 12
201717,87663.8%12 of 12
201815,78156.3%12 of 12
201920,78974.2%12 of 12
202024,32986.6%12 of 12
202122,83081.4%12 of 12
202222,77381.2%12 of 12
202318,56466.2%12 of 12
202419,32768.8%12 of 12
202512,93846.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · PJM

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
UNT1Landfill Gas0.8March 1993
UNT2Landfill Gas0.8March 1993
UNT3Landfill Gas0.8March 1993
UNT4Landfill Gas0.8March 1993

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists NextEra Renewable Fuels, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query I 95 Landfill Phase II and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near I 95 Landfill Phase II

More plants operated by NextEra Renewable Fuels, LLC

Questions about I 95 Landfill Phase II

How much power does I 95 Landfill Phase II produce?

I 95 Landfill Phase II reported 12,938 MWh (12.9 GWh) of net generation in 2025, a 46.2% capacity factor on 3.2 MW of nameplate capacity.

Where is I 95 Landfill Phase II?

I 95 Landfill Phase II is in Fairfax County, Virginia, at 38.6892, −77.2375. It is in the PJM Interconnection, LLC balancing area (PJM).

Who operates I 95 Landfill Phase II?

EIA-860M for August 2026 lists NextEra Renewable Fuels, LLC as the operator (EIA operator ID 57249). The operator is not always the owner.

When did I 95 Landfill Phase II start operating?

Its first generator began operating in March 1993, according to EIA-860M.

Does InfraMap have power prices for I 95 Landfill Phase II?

Yes. InfraMap has PJM day-ahead and real-time prices at 1 price node linked to I 95 Landfill Phase II, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • PJM day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page