HydroOperatingTVA

Chilhowee

Hydro power plant in Blount County, Tennessee. 49.8 MW of nameplate capacity across 3 generators, operated by Brookfield Smoky Mountain Hydropower LP.

Also known as Chilhowee Power Plant · EIA plant 54901

Analyst: free account, 1 question a day.

CalderwoodCheoahSR MaryvilleSR Blount, LLCFontana DamChilhowee10 km
Open in the map
6 plants within 25 km, from EIA coordinates.

Key facts

Capacity
49.8 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
August 1957First generator online
Operator
Brookfield Smoky Mountain Hydropower LPEIA operator ID 306
Grid
TVABalancing authority TVA
Price nodes
None linkedNo verified ISO node
Location
Blount County, TN35.5453, −84.0503
EIA plant ID
54901EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Chilhowee produces

Free · EIA-923

Net generation, 2025

158 GWh

157,680 MWh, final

Capacity factor, 2025

36.1%

2024: 36.4%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

11.0–252.5

GWh a year. Low 2016, high 2020

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000118,212Not reported12 of 12
200194,452Not reported12 of 12
2002148,985Not reported12 of 12
2003209,200Not reported12 of 12
2004186,264Not reported12 of 12
2005184,408Not reported12 of 12
2006131,060Not reported12 of 12
200790,031Not reported12 of 12
2008102,539Not reported12 of 12
2009194,196Not reported12 of 12
2010162,30337.2%12 of 12
2011155,11935.6%12 of 12
2012139,43031.9%12 of 12
2013240,90955.2%12 of 12
2014151,78334.8%12 of 12
201597,99822.5%12 of 12
201611,0162.5%12 of 12
201778,46918.0%12 of 12
2018194,46744.6%12 of 12
2019219,77050.4%12 of 12
2020252,49757.7%12 of 12
2021201,68346.2%12 of 12
2022163,96537.6%12 of 12
2023146,93533.7%12 of 12
2024159,11536.4%12 of 12
2025157,68036.1%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Hydroelectric16.6August 1957
2Conventional Hydroelectric16.6October 1957
3Conventional Hydroelectric16.6September 1957

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Brookfield Smoky Mountain Hydropower LP as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Chilhowee and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Chilhowee

More plants operated by Brookfield Smoky Mountain Hydropower LP

Questions about Chilhowee

How much power does Chilhowee produce?

Chilhowee reported 157,680 MWh (158 GWh) of net generation in 2025, a 36.1% capacity factor on 49.8 MW of nameplate capacity.

Where is Chilhowee?

Chilhowee is in Blount County, Tennessee, at 35.5453, −84.0503. It is in the Tennessee Valley Authority balancing area (TVA).

Who operates Chilhowee?

EIA-860M for August 2026 lists Brookfield Smoky Mountain Hydropower LP as the operator (EIA operator ID 306). The operator is not always the owner.

When did Chilhowee start operating?

Its first generator began operating in August 1957, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page