Natural gasOperatingERCOT

Frontera Energy Center

Natural gas power plant in Hidalgo County, Texas. 529 MW of nameplate capacity across 3 generators, operated by Frontera Generation Limited Partnership.

Also known as Energia Buenavista · EIA plant 55098

Analyst: free account, 1 question a day.

Palmview BESSRegis Goodwin LLCSMT Mission LLCMadero GridFrontera5 km
Open in the map
6 plants within 8.7 km, from EIA coordinates.

Key facts

Capacity
529 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
June 1999First generator online
Operator
Frontera Generation Limited PartnershipEIA operator ID 6519
Grid
ERCOTBalancing authority ERCO
Price nodes
None linkedNo verified ISO node
Location
Hidalgo County, TX26.2080, −98.3992
EIA plant ID
55098EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Frontera produces

Free · EIA-923

Net generation, 2025

1.96 TWh

1,958,986 MWh, final

Capacity factor, 2025

42.3%

2024: 48.8%

January to July 2026

860 GWh

Provisional

Range, 2015 to 2025

2.0–3.3

TWh a year. Low 2025, high 2015

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20001,289,992Not reported12 of 12
20011,654,481Not reported12 of 12
20021,345,813Not reported12 of 12
20031,249,719Not reported12 of 12
20041,059,487Not reported12 of 12
20051,594,294Not reported12 of 12
20062,036,942Not reported12 of 12
20072,309,132Not reported12 of 12
2008183,892Not reported1 of 12
20092,212,874Not reported12 of 12
20102,001,39443.2%12 of 12
20112,412,37352.1%12 of 12
20123,060,83165.9%12 of 12
20132,864,362Not reported12 of 12
20142,678,53157.8%12 of 12
20153,274,47170.7%12 of 12
20162,103,478Not reported10 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
20231,072,50739.5%7 of 12
20242,266,17048.8%12 of 12
20251,958,98642.3%12 of 12
2026 (provisional, partial year)859,52431.9%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

1,420

million gallons

Consumption, 2024

1,025

million gallons

Source

Rio Grande River - Hidalgo Irr Dist

Surface, Fresh. Induced-draft tower

Watershed stress

Severe · 0.830

USGS SUI, HUC12 Llano Grande Lake-Arroyo Colorado

12 of 12 cooling months report withdrawal. SUI of the HUC12 containing the plant. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Natural Gas Fired Combined Cycle172.0June 1999
GEN2Natural Gas Fired Combined Cycle172.0July 1999
GEN3Natural Gas Fired Combined Cycle185.0May 2000

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Frontera Generation Limited Partnership as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Frontera Energy Center and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Frontera

Questions about Frontera

How much power does Frontera Energy Center produce?

Frontera Energy Center reported 1,958,986 MWh (1.96 TWh) of net generation in 2025, a 42.3% capacity factor on 529 MW of nameplate capacity. From January to July 2026 it reported 860 GWh, which is provisional.

Where is Frontera Energy Center?

Frontera Energy Center is in Hidalgo County, Texas, at 26.2080, −98.3992. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Frontera Energy Center?

EIA-860M for August 2026 lists Frontera Generation Limited Partnership as the operator (EIA operator ID 6519). The operator is not always the owner.

When did Frontera Energy Center start operating?

Its first generator began operating in June 1999, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page