Vansycle
Wind power plant in Umatilla County, Oregon. 25 MW of nameplate capacity across 1 generator, operated by ESI Vansycle Partners LP.
Also known as Vansycle Wind Farm · Vansycle I · EIA plant 55125
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 25 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- August 1998First generator online
- Operator
- ESI Vansycle Partners LPEIA operator ID 6017
- Grid
- BPATBalancing authority BPAT
- Price nodes
- None linkedNo verified ISO node
- Location
- Umatilla County, OR45.9362, −118.6600
- EIA plant ID
- 55125EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Vansycle produces
Free · EIA-923Net generation, 2025
54.9 GWh
54,901 MWh, final
Capacity factor, 2025
25.1%
2024: 27.3%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2015 to 2025
54.9–83.6
GWh a year. Low 2025, high 2020
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | 70,246 | Not reported | 12 of 12 |
| 2002 | 73,325 | Not reported | 12 of 12 |
| 2003 | 74,348 | Not reported | 12 of 12 |
| 2004 | 76,217 | Not reported | 12 of 12 |
| 2005 | 69,111 | Not reported | 12 of 12 |
| 2006 | 66,228 | Not reported | 12 of 12 |
| 2007 | 70,486 | Not reported | 12 of 12 |
| 2008 | 78,544 | Not reported | 12 of 12 |
| 2009 | 68,884 | Not reported | 12 of 12 |
| 2010 | 73,857 | 33.7% | 12 of 12 |
| 2011 | 39,038 | 17.8% | 12 of 12 |
| 2012 | 69,380 | 31.6% | 12 of 12 |
| 2013 | 63,440 | 29.0% | 12 of 12 |
| 2014 | 67,562 | 30.9% | 12 of 12 |
| 2015 | 62,338 | 28.5% | 12 of 12 |
| 2016 | 76,522 | 34.8% | 12 of 12 |
| 2017 | 63,777 | 29.1% | 12 of 12 |
| 2018 | 67,548 | 30.8% | 12 of 12 |
| 2019 | 57,529 | 26.3% | 12 of 12 |
| 2020 | 83,624 | 38.1% | 12 of 12 |
| 2021 | 68,658 | 31.4% | 12 of 12 |
| 2022 | 61,203 | 27.9% | 12 of 12 |
| 2023 | 61,721 | 28.2% | 12 of 12 |
| 2024 | 59,989 | 27.3% | 12 of 12 |
| 2025 | 54,901 | 25.1% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| WGNS | Onshore Wind Turbine | 25.0 | August 1998 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists ESI Vansycle Partners LP as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Vansycle and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Vansycle
Questions about Vansycle
How much power does Vansycle produce?
Vansycle reported 54,901 MWh (54.9 GWh) of net generation in 2025, a 25.1% capacity factor on 25 MW of nameplate capacity.
Where is Vansycle?
Vansycle is in Umatilla County, Oregon, at 45.9362, −118.6600. It is in the Bonneville Power Administration balancing area (BPAT).
Who operates Vansycle?
EIA-860M for August 2026 lists ESI Vansycle Partners LP as the operator (EIA operator ID 6017). The operator is not always the owner.
When did Vansycle start operating?
Its first generator began operating in August 1998, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
- Project names from the USGS U.S. Wind Turbine Database
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page