Natural gasOperatingGRID

Hermiston Power Partnership

Natural gas power plant in Umatilla County, Oregon. 689.4 MW of nameplate capacity across 3 generators, operated by Hermiston Power Partnership.

Also known as Hermiston Power Projects · EIA plant 55328

Analyst: free account, 1 question a day.

Hermiston Generating…Four Corners Windfarm LLCOregon Trail Windfarm LLCWard Butte Windfarm LLCNorWest Energy 9 LLCHermiston Power Partnership5 km
Open in the map
6 plants within 14 km, from EIA coordinates.

Key facts

Capacity
689.4 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
August 2002First generator online
Operator
Hermiston Power PartnershipEIA operator ID 7869
Grid
GRIDBalancing authority GRID
Price nodes
None linkedNo verified ISO node
Location
Umatilla County, OR45.7940, −119.3133
EIA plant ID
55328EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Hermiston Power Partnership produces

Free · EIA-923

Net generation, 2025

2.99 TWh

2,988,998 MWh, final

Capacity factor, 2025

49.5%

2024: 70.7%

January to July 2026

1.85 TWh

Provisional

Range, 2016 to 2025

3.0–4.3

TWh a year. Low 2017, high 2021

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
20032,563,676Not reported12 of 12
20043,986,389Not reported12 of 12
20053,569,997Not reported12 of 12
20062,905,519Not reported12 of 12
20073,078,085Not reported12 of 12
20083,720,166Not reported12 of 12
20093,466,411Not reported12 of 12
20103,241,57353.7%12 of 12
20111,155,91919.1%12 of 12
20122,888,90347.7%12 of 12
20133,655,689Not reported12 of 12
20143,100,58451.3%12 of 12
2015330,67064.5%1 of 12
20163,179,73452.5%12 of 12
20172,970,80649.2%12 of 12
20183,644,23660.3%12 of 12
20194,298,26471.2%12 of 12
20203,956,21865.3%12 of 12
20214,341,07271.9%12 of 12
20223,859,81163.9%12 of 12
20233,918,10664.9%12 of 12
20244,283,08070.7%12 of 12
20252,988,99849.5%12 of 12
2026 (provisional, partial year)1,851,08352.8%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

CO₂, 2025

1.32M

US short tons. 2024: 1.88M

SO₂, 2025

7

US short tons

NOx, 2025

174

US short tons

CO₂ per MWh, calculated

0.44 t

About 883 lb per MWh

2 of 2 EPA units reported CO₂ in 2025 (CTG-1, CTG-2), matched to EIA plant 55328 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

921

million gallons

Consumption, 2024

793

million gallons

Source

Municipal

Surface, Fresh. Induced-draft tower

Watershed stress

Moderate · 0.409

USGS SUI, HUC12 Umatilla River

12 of 12 cooling months report withdrawal. SUI of the HUC12 containing the plant. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
CTG1Natural Gas Fired Combined Cycle212.5August 2002
CTG2Natural Gas Fired Combined Cycle212.5August 2002
STG1Natural Gas Fired Combined Cycle264.4August 2002

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Hermiston Power Partnership as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Hermiston Power Partnership and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Hermiston Power Partnership

Questions about Hermiston Power Partnership

How much power does Hermiston Power Partnership produce?

Hermiston Power Partnership reported 2,988,998 MWh (2.99 TWh) of net generation in 2025, a 49.5% capacity factor on 689.4 MW of nameplate capacity. From January to July 2026 it reported 1.85 TWh, which is provisional.

Where is Hermiston Power Partnership?

Hermiston Power Partnership is in Umatilla County, Oregon, at 45.7940, −119.3133. It is in the Gridforce Energy Management, LLC balancing area (GRID).

Who operates Hermiston Power Partnership?

EIA-860M for August 2026 lists Hermiston Power Partnership as the operator (EIA operator ID 7869). The operator is not always the owner.

When did Hermiston Power Partnership start operating?

Its first generator began operating in August 2002, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page