Landfill gasOperatingMISO

Oak Ridge LFGTE

Landfill gas power plant in Cass County, Indiana. 3.2 MW of nameplate capacity across 4 generators, operated by Wabash Valley Power Assn, Inc.

Also known as EIA plant 56463

Analyst: free account, 1 question a day.

Logansport SolarAppleseed SolarKokomo Solar 1, LLCOak Ridge LFGTE10 km
Open in the map
6 plants within 32 km, from EIA coordinates.

Key facts

Capacity
3.2 MWNameplate
Generators
4 operatingEIA-860M, August 2026
Operating since
December 2003First generator online
Operator
Wabash Valley Power Assn, IncEIA operator ID 40211
Grid
MISOBalancing authority MISO
Price nodes
1 MISO nodeResource nodes with prices
Location
Cass County, IN40.7213, −86.3421
EIA plant ID
56463EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Oak Ridge LFGTE produces

Free · EIA-923

Net generation, 2025

23.0 GWh

22,995 MWh, final

Capacity factor, 2025

82.0%

2024: 91.7%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

19.0–25.8

GWh a year. Low 2016, high 2024

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
200626,843Not reported12 of 12
200726,250Not reported12 of 12
200826,362Not reported12 of 12
200926,042Not reported12 of 12
201024,88788.8%12 of 12
201123,57484.1%12 of 12
201222,64780.6%12 of 12
201321,37176.2%12 of 12
201422,32979.7%12 of 12
201520,87274.5%12 of 12
201619,00567.6%12 of 12
201720,40572.8%12 of 12
201820,51373.2%12 of 12
201921,81977.8%12 of 12
202025,39290.3%12 of 12
202123,36783.4%12 of 12
202223,63584.3%12 of 12
202321,72277.5%12 of 12
202425,78991.7%12 of 12
202522,99582.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Landfill Gas0.8December 2003
2Landfill Gas0.8December 2003
3Landfill Gas0.8December 2003
4Landfill Gas0.8December 2003

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Wabash Valley Power Assn, Inc as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Oak Ridge LFGTE and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Oak Ridge LFGTE

More plants operated by Wabash Valley Power Assn, Inc

Questions about Oak Ridge LFGTE

How much power does Oak Ridge LFGTE produce?

Oak Ridge LFGTE reported 22,995 MWh (23.0 GWh) of net generation in 2025, a 82.0% capacity factor on 3.2 MW of nameplate capacity.

Where is Oak Ridge LFGTE?

Oak Ridge LFGTE is in Cass County, Indiana, at 40.7213, −86.3421. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Oak Ridge LFGTE?

EIA-860M for August 2026 lists Wabash Valley Power Assn, Inc as the operator (EIA operator ID 40211). The operator is not always the owner.

When did Oak Ridge LFGTE start operating?

Its first generator began operating in December 2003, according to EIA-860M.

Does InfraMap have power prices for Oak Ridge LFGTE?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Oak Ridge LFGTE, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page