WindOperatingPSCO

Cedar Point Wind

Wind power plant in Lincoln County, Colorado. 252 MW of nameplate capacity across 1 generator, operated by Cedar Point LLC.

Also known as Cedar Point Wind Farm · Cedar Point · EIA plant 57315

Analyst: free account, 1 question a day.

Limon Wind ILimon Wind IILimon III Wind LLCLimon Generating StationRush Creek WindTitan SolarCedar Point Wind20 km
Open in the map
6 plants within 41 km, from EIA coordinates.

Key facts

Capacity
252 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
May 2011First generator online
Operator
Cedar Point LLCEIA operator ID 56662
Grid
PSCOBalancing authority PSCO
Price nodes
None linkedNo verified ISO node
Location
Lincoln County, CO39.4218, −103.6781
EIA plant ID
57315EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Cedar Point Wind produces

Free · EIA-923

Net generation, 2025

693 GWh

692,569 MWh, final

Capacity factor, 2025

31.4%

2024: 30.3%

January to July 2026

367 GWh

Provisional

Range, 2015 to 2025

494.7–743.7

GWh a year. Low 2022, high 2017

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011316,018Not reported8 of 12
2012867,70939.2%12 of 12
2013757,47234.3%12 of 12
2014764,23434.6%12 of 12
2015645,03529.2%12 of 12
2016661,31829.9%12 of 12
2017743,68633.7%12 of 12
2018726,65632.9%12 of 12
2019589,97626.7%12 of 12
2020710,18132.1%12 of 12
2021495,99922.5%12 of 12
2022494,74022.4%12 of 12
2023589,65226.7%12 of 12
2024670,50730.3%12 of 12
2025692,56931.4%12 of 12
2026 (provisional, partial year)366,55928.6%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1-139Onshore Wind Turbine252.0May 2011

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Cedar Point LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Cedar Point Wind and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Cedar Point Wind

Questions about Cedar Point Wind

How much power does Cedar Point Wind produce?

Cedar Point Wind reported 692,569 MWh (693 GWh) of net generation in 2025, a 31.4% capacity factor on 252 MW of nameplate capacity. From January to July 2026 it reported 367 GWh, which is provisional.

Where is Cedar Point Wind?

Cedar Point Wind is in Lincoln County, Colorado, at 39.4218, −103.6781. It is in the Public Service Company of Colorado balancing area (PSCO).

Who operates Cedar Point Wind?

EIA-860M for August 2026 lists Cedar Point LLC as the operator (EIA operator ID 56662). The operator is not always the owner.

When did Cedar Point Wind start operating?

Its first generator began operating in May 2011, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page