McGinness Hills

Geothermal power plant in Lander County, Nevada. 104 MW of nameplate capacity across 6 generators, operated by Ormat Nevada Inc.

Also known as EIA plant 57446

Analyst: free account, 1 question a day.

McGinness Hills 3McGinness Hills1 km
Open in the map
1 plant within 1.6 km, from EIA coordinates.

Key facts

Capacity
104 MWNameplate
Generators
6 operatingEIA-860M, August 2026
Operating since
May 2012First generator online
Operator
Ormat Nevada IncEIA operator ID 34691
Grid
NEVPBalancing authority NEVP
Price nodes
None linkedNo verified ISO node
Location
Lander County, NV39.5911, −116.9119
EIA plant ID
57446EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power McGinness Hills produces

Free · EIA-923

Net generation, 2025

569 GWh

568,628 MWh, final

Capacity factor, 2025

62.4%

2024: 66.0%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

568.6–765.2

GWh a year. Low 2025, high 2017

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012159,074Not reported7 of 12
2013327,09071.8%12 of 12
2014325,49571.5%12 of 12
2015666,960Not reported12 of 12
2016759,20486.4%12 of 12
2017765,23987.4%12 of 12
2018737,85384.2%12 of 12
2019758,18786.6%12 of 12
2020719,36981.9%12 of 12
2021675,17077.1%12 of 12
2022665,05175.9%12 of 12
2023642,454Not reported12 of 12
2024602,82266.0%12 of 12
2025568,62862.4%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Geothermal20.0May 2012
2Geothermal20.0June 2012
3Geothermal12.0June 2012
OE23RGeothermal16.0September 2023
OEC21Geothermal18.0February 2015
OEC22Geothermal18.0February 2015

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Ormat Nevada Inc as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query McGinness Hills and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near McGinness Hills

More plants operated by Ormat Nevada Inc

Questions about McGinness Hills

How much power does McGinness Hills produce?

McGinness Hills reported 568,628 MWh (569 GWh) of net generation in 2025, a 62.4% capacity factor on 104 MW of nameplate capacity.

Where is McGinness Hills?

McGinness Hills is in Lander County, Nevada, at 39.5911, −116.9119. It is in the Nevada Power Company balancing area (NEVP).

Who operates McGinness Hills?

EIA-860M for August 2026 lists Ormat Nevada Inc as the operator (EIA operator ID 34691). The operator is not always the owner.

When did McGinness Hills start operating?

Its first generator began operating in May 2012, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page