Key facts

Capacity
200 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
January 2012First generator online
Operator
Caney River Wind ProjectEIA operator ID 57191
Grid
SPPBalancing authority SWPP
Price nodes
1 SPP nodeResource nodes with prices
Location
Elk County, KS37.4600, −96.4200
EIA plant ID
57858EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Caney River Wind Project produces

Free · EIA-923

Net generation, 2025

564 GWh

564,297 MWh, final

Capacity factor, 2025

32.2%

2024: 36.2%

January to July 2026

416 GWh

Provisional

Range, 2015 to 2025

564.3–754.1

GWh a year. Low 2025, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
201125,906Not reported12 of 12
2012663,94141.3%11 of 12
2013732,62641.8%12 of 12
2014744,54642.5%12 of 12
2015686,08639.2%12 of 12
2016696,32639.6%12 of 12
2017736,59742.0%12 of 12
2018637,98336.4%12 of 12
2019656,59337.5%12 of 12
2020695,97239.6%12 of 12
2021672,56238.4%12 of 12
2022754,08343.0%12 of 12
2023675,24338.5%12 of 12
2024636,44036.2%12 of 12
2025564,29732.2%12 of 12
2026 (provisional, partial year)415,93840.9%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · SPP

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Onshore Wind Turbine200.0January 2012

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Caney River Wind Project as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Caney River Wind Project and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Caney River Wind Project

Questions about Caney River Wind Project

How much power does Caney River Wind Project produce?

Caney River Wind Project reported 564,297 MWh (564 GWh) of net generation in 2025, a 32.2% capacity factor on 200 MW of nameplate capacity. From January to July 2026 it reported 416 GWh, which is provisional.

Where is Caney River Wind Project?

Caney River Wind Project is in Elk County, Kansas, at 37.4600, −96.4200. It is in the Southwest Power Pool balancing area (SWPP).

Who operates Caney River Wind Project?

EIA-860M for August 2026 lists Caney River Wind Project as the operator (EIA operator ID 57191). The operator is not always the owner.

When did Caney River Wind Project start operating?

Its first generator began operating in January 2012, according to EIA-860M.

Does InfraMap have power prices for Caney River Wind Project?

Yes. InfraMap has SPP day-ahead and real-time prices at 1 price node linked to Caney River Wind Project, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • SPP day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page