Landfill gasOperatingPJM

Millersville LFG

Landfill gas power plant in Anne Arundel County, Maryland. 3.2 MW of nameplate capacity across 2 generators, operated by LES Operations Services LLC.

Also known as EIA plant 58246

Analyst: free account, 1 question a day.

7448 Candlewood RoadBowie State SolarCromwellAirport Commons 7-slbal210Millersville LFG5 km
Open in the map
6 plants within 13 km, from EIA coordinates.

Key facts

Capacity
3.2 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
July 2012First generator online
Operator
LES Operations Services LLCEIA operator ID 58221
Grid
PJMBalancing authority PJM
Price nodes
1 PJM nodeResource nodes with prices
Location
Anne Arundel County, MD39.0847, −76.6764
EIA plant ID
58246EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Millersville LFG produces

Free · EIA-923

Net generation, 2025

20.9 GWh

20,895 MWh, final

Capacity factor, 2025

74.5%

2024: 65.5%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

18.4–26.5

GWh a year. Low 2024, high 2017

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
201212,717Not reported6 of 12
201325,95392.6%12 of 12
201426,44194.3%12 of 12
201525,93592.5%12 of 12
201626,01292.5%12 of 12
201726,52794.6%12 of 12
201825,99692.7%12 of 12
201925,99292.7%12 of 12
202024,33186.6%12 of 12
202123,79084.9%12 of 12
202223,18582.7%12 of 12
202322,06678.7%12 of 12
202418,41565.5%12 of 12
202520,89574.5%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · PJM

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
CAT1Landfill Gas1.6July 2012
CAT2Landfill Gas1.6July 2012

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists LES Operations Services LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Millersville LFG and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Millersville LFG

Questions about Millersville LFG

How much power does Millersville LFG produce?

Millersville LFG reported 20,895 MWh (20.9 GWh) of net generation in 2025, a 74.5% capacity factor on 3.2 MW of nameplate capacity.

Where is Millersville LFG?

Millersville LFG is in Anne Arundel County, Maryland, at 39.0847, −76.6764. It is in the PJM Interconnection, LLC balancing area (PJM).

Who operates Millersville LFG?

EIA-860M for August 2026 lists LES Operations Services LLC as the operator (EIA operator ID 58221). The operator is not always the owner.

When did Millersville LFG start operating?

Its first generator began operating in July 2012, according to EIA-860M.

Does InfraMap have power prices for Millersville LFG?

Yes. InfraMap has PJM day-ahead and real-time prices at 1 price node linked to Millersville LFG, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • PJM day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page