HydroOperatingPACW

45 Mile Hydroelectric Project

Hydro power plant in Jefferson County, Oregon. 3 MW of nameplate capacity across 3 generators, operated by EBD Hydro LLC.

Also known as EIA plant 58455

Analyst: free account, 1 question a day.

Green Solar LLC (CSG)Elbe Solar CenterRound ButteAdams Solar CenterPelton45 Mile Hydroelectric…10 km
Open in the map
6 plants within 20 km, from EIA coordinates.

Key facts

Capacity
3 MWNameplate
Generators
3 operatingEIA-860M, August 2026
Operating since
May 2015First generator online
Operator
EBD Hydro LLCEIA operator ID 58443
Grid
PACWBalancing authority PACW
Price nodes
None linkedNo verified ISO node
Location
Jefferson County, OR44.5281, −121.1528
EIA plant ID
58455EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power 45 Mile Hydroelectric Project produces

Free · EIA-923

Net generation, 2025

5.04 GWh

5,044 MWh, final

Capacity factor, 2025

19.2%

2024: 18.7%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2016 to 2025

4.1–7.9

GWh a year. Low 2022, high 2018

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
20155,561Not reported8 of 12
20167,33227.8%12 of 12
20176,34924.2%12 of 12
20187,92130.1%12 of 12
20195,32420.3%12 of 12
20204,90518.6%12 of 12
20214,18815.9%12 of 12
20224,05715.4%12 of 12
20234,22316.1%12 of 12
20244,93618.7%12 of 12
20255,04419.2%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
0001Conventional Hydroelectric1.0May 2015
0002Conventional Hydroelectric1.0May 2015
0003Conventional Hydroelectric1.0May 2015

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists EBD Hydro LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query 45 Mile Hydroelectric Project and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near 45 Mile Hydroelectric Project

Questions about 45 Mile Hydroelectric Project

How much power does 45 Mile Hydroelectric Project produce?

45 Mile Hydroelectric Project reported 5,044 MWh (5.04 GWh) of net generation in 2025, a 19.2% capacity factor on 3 MW of nameplate capacity.

Where is 45 Mile Hydroelectric Project?

45 Mile Hydroelectric Project is in Jefferson County, Oregon, at 44.5281, −121.1528. It is in the PacifiCorp - West balancing area (PACW).

Who operates 45 Mile Hydroelectric Project?

EIA-860M for August 2026 lists EBD Hydro LLC as the operator (EIA operator ID 58443). The operator is not always the owner.

When did 45 Mile Hydroelectric Project start operating?

Its first generator began operating in May 2015, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page