Silver State Solar Power South

Solar power plant in Clark County, Nevada. 260.1 MW of nameplate capacity across 8 generators, operated by Silver State Solar Power South, LLC.

Also known as Silver State South Solar Project · EIA plant 58644

Analyst: free account, 1 question a day.

Silver State South StorageHiggins Generating StationStateline SolarIvanpah 3Ivanpah 2Ivanpah 1Silver State Solar Po…10 km
Open in the map
6 plants within 16 km, from EIA coordinates.

Key facts

Capacity
260.1 MWNameplate
Generators
8 operatingEIA-860M, August 2026
Operating since
November 2015First generator online
Operator
Silver State Solar Power South, LLCEIA operator ID 59363
Grid
CAISOBalancing authority CISO
Price nodes
1 CAISO nodeResource nodes with prices
Location
Clark County, NV35.6300, −115.3200
EIA plant ID
58644EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Silver State Solar Power South produces

Free · EIA-923

Net generation, 2025

684 GWh

684,062 MWh, final

Capacity factor, 2025

30.0%

2024: 27.5%

January to July 2026

378 GWh

Provisional

Range, 2016 to 2025

558.6–711.2

GWh a year. Low 2016, high 2017

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
20158,595Not reported2 of 12
2016558,588Not reported12 of 12
2017711,15932.5%12 of 12
2018710,89432.5%12 of 12
2019654,772Not reported12 of 12
2020679,95129.8%12 of 12
2021671,95129.5%12 of 12
2022636,96628.0%12 of 12
2023643,60628.2%12 of 12
2024629,33927.5%12 of 12
2025684,06230.0%12 of 12
2026 (provisional, partial year)378,26128.6%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · CAISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
BLK1Solar Photovoltaic26.4November 2015
BLK2Solar Photovoltaic27.9December 2015
BLK3Solar Photovoltaic37.2December 2015
BLK4Solar Photovoltaic35.7January 2016
BLK5Solar Photovoltaic35.0April 2016
BLK6Solar Photovoltaic36.6April 2016
BLK7Solar Photovoltaic35.0May 2016
BLK8Solar Photovoltaic26.3June 2016

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Silver State Solar Power South, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Silver State Solar Power South and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Silver State Solar Power South

Questions about Silver State Solar Power South

How much power does Silver State Solar Power South produce?

Silver State Solar Power South reported 684,062 MWh (684 GWh) of net generation in 2025, a 30.0% capacity factor on 260.1 MW of nameplate capacity. From January to July 2026 it reported 378 GWh, which is provisional.

Where is Silver State Solar Power South?

Silver State Solar Power South is in Clark County, Nevada, at 35.6300, −115.3200. It is in the California Independent System Operator balancing area (CISO).

Who operates Silver State Solar Power South?

EIA-860M for August 2026 lists Silver State Solar Power South, LLC as the operator (EIA operator ID 59363). The operator is not always the owner.

When did Silver State Solar Power South start operating?

Its first generator began operating in November 2015, according to EIA-860M.

Does InfraMap have power prices for Silver State Solar Power South?

Yes. InfraMap has CAISO day-ahead and real-time prices at 1 price node linked to Silver State Solar Power South, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • CAISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page