Key facts
- Capacity
- 2 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- June 2005First generator online
- Operator
- East Kansas Agri-Energy, LLCEIA operator ID 59160
- Grid
- SPPBalancing authority SWPP
- Price nodes
- None linkedNo verified ISO node
- Location
- Anderson County, KS38.2725, −95.2403
- EIA plant ID
- 59383EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power East Kansas Agri-Energy produces
Free · EIA-923Net generation, 2025
4.99 GWh
4,990 MWh, final
Capacity factor, 2025
28.5%
2024: 28.4%
January to July 2026
2.91 GWh
Provisional
Range, 2015 to 2025
0.0–5.0
GWh a year. Low 2015, high 2018
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | 1 | 0.0% | 12 of 12 |
| 2015 | 0 | 0.0% | 12 of 12 |
| 2016 | 1 | 0.0% | 12 of 12 |
| 2017 | 4,732 | 27.0% | 12 of 12 |
| 2018 | 5,010 | 28.6% | 12 of 12 |
| 2019 | 4,996 | 28.5% | 12 of 12 |
| 2020 | 4,971 | 28.3% | 12 of 12 |
| 2021 | 4,978 | 28.4% | 12 of 12 |
| 2022 | 829 | 4.7% | 12 of 12 |
| 2023 | 3,118 | 17.8% | 12 of 12 |
| 2024 | 4,990 | 28.4% | 12 of 12 |
| 2025 | 4,990 | 28.5% | 12 of 12 |
| 2026 (provisional, partial year) | 2,910 | 28.6% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| KATO | All Other | 2.0 | June 2005 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists East Kansas Agri-Energy, LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Generation potential vs reported
Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.
300 analyst questions a month, plus MCP
Query East Kansas Agri-Energy, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near East Kansas Agri-Energy
Questions about East Kansas Agri-Energy
How much power does East Kansas Agri-Energy, LLC produce?
East Kansas Agri-Energy, LLC reported 4,990 MWh (4.99 GWh) of net generation in 2025, a 28.5% capacity factor on 2 MW of nameplate capacity. From January to July 2026 it reported 2.91 GWh, which is provisional.
Where is East Kansas Agri-Energy, LLC?
East Kansas Agri-Energy, LLC is in Anderson County, Kansas, at 38.2725, −95.2403. It is in the Southwest Power Pool balancing area (SWPP).
Who operates East Kansas Agri-Energy, LLC?
EIA-860M for August 2026 lists East Kansas Agri-Energy, LLC as the operator (EIA operator ID 59160). The operator is not always the owner.
When did East Kansas Agri-Energy, LLC start operating?
Its first generator began operating in June 2005, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page