Landfill gasOperatingDUK

COC Surry LFG, LLC

Landfill gas power plant in Surry County, North Carolina. 1.6 MW of nameplate capacity across 1 generator, operated by Petra Engineering.

Also known as EIA plant 59439

Analyst: free account, 1 question a day.

Ararat Rock Solar, LLCMayberry Solar LLCDouble CreekHayes Solar, LLCStony Knoll Solar, LLCTwo Hearted SolarCOC Surry LFG10 km
Open in the map
6 plants within 23 km, from EIA coordinates.

Key facts

Capacity
1.6 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
May 2013First generator online
Operator
Petra EngineeringEIA operator ID 59177
Grid
DUKBalancing authority DUK
Price nodes
None linkedNo verified ISO node
Location
Surry County, NC36.4386, −80.5683
EIA plant ID
59439EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power COC Surry LFG produces

Free · EIA-923

Net generation, 2025

8.32 GWh

8,315 MWh, final

Capacity factor, 2025

59.3%

2024: 62.7%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

5.7–8.8

GWh a year. Low 2022, high 2024

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
20146,92049.4%12 of 12
20157,56153.9%12 of 12
20167,00149.8%12 of 12
20176,35445.3%12 of 12
20186,77148.3%12 of 12
20198,17058.3%12 of 12
20207,29751.9%12 of 12
20216,31345.0%12 of 12
20225,72440.8%12 of 12
20237,62354.4%12 of 12
20248,81262.7%12 of 12
20258,31559.3%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
UNIT1Landfill Gas1.6May 2013

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Petra Engineering as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query COC Surry LFG, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near COC Surry LFG

Questions about COC Surry LFG

How much power does COC Surry LFG, LLC produce?

COC Surry LFG, LLC reported 8,315 MWh (8.32 GWh) of net generation in 2025, a 59.3% capacity factor on 1.6 MW of nameplate capacity.

Where is COC Surry LFG, LLC?

COC Surry LFG, LLC is in Surry County, North Carolina, at 36.4386, −80.5683. It is in the Duke Energy Carolinas balancing area (DUK).

Who operates COC Surry LFG, LLC?

EIA-860M for August 2026 lists Petra Engineering as the operator (EIA operator ID 59177). The operator is not always the owner.

When did COC Surry LFG, LLC start operating?

Its first generator began operating in May 2013, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page