Springer Solar 1
Solar power plant in Colfax County, New Mexico. 1 MW of nameplate capacity across 1 generator, operated by Springer Electric Coop, Inc.
Also known as Springer Solar Farm · EIA plant 59560
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 1 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- May 2015First generator online
- Operator
- Springer Electric Coop, IncEIA operator ID 17826
- Grid
- PNMBalancing authority PNM
- Price nodes
- None linkedNo verified ISO node
- Location
- Colfax County, NM36.3981, −104.5942
- EIA plant ID
- 59560EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Springer Solar 1 produces
Free · EIA-923Net generation, 2025
2.17 GWh
2,171 MWh, final
Capacity factor, 2025
24.8%
2024: 23.1%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2016 to 2025
2.0–2.6
GWh a year. Low 2024, high 2016
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | 1,670 | Not reported | 8 of 12 |
| 2016 | 2,581 | 29.4% | 12 of 12 |
| 2017 | 2,493 | 28.5% | 12 of 12 |
| 2018 | 2,538 | 29.0% | 12 of 12 |
| 2019 | 2,455 | 28.0% | 12 of 12 |
| 2020 | 2,498 | 28.4% | 12 of 12 |
| 2021 | 2,432 | 27.8% | 12 of 12 |
| 2022 | 2,296 | 26.2% | 12 of 12 |
| 2023 | 2,204 | 25.2% | 12 of 12 |
| 2024 | 2,029 | 23.1% | 12 of 12 |
| 2025 | 2,171 | 24.8% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| SPRG1 | Solar Photovoltaic | 1.0 | May 2015 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Springer Electric Coop, Inc as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Springer Solar 1 and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Springer Solar 1
Questions about Springer Solar 1
How much power does Springer Solar 1 produce?
Springer Solar 1 reported 2,171 MWh (2.17 GWh) of net generation in 2025, a 24.8% capacity factor on 1 MW of nameplate capacity.
Where is Springer Solar 1?
Springer Solar 1 is in Colfax County, New Mexico, at 36.3981, −104.5942. It is in the Public Service Company of New Mexico balancing area (PNM).
Who operates Springer Solar 1?
EIA-860M for August 2026 lists Springer Electric Coop, Inc as the operator (EIA operator ID 17826). The operator is not always the owner.
When did Springer Solar 1 start operating?
Its first generator began operating in May 2015, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page