Harvest Ridge Wind Farm
Wind power plant in Douglas County, Illinois. 202 MW of nameplate capacity across 1 generator, operated by Harvest Ridge Wind Farm.
Also known as Broadlands · EIA plant 61161
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 202 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- July 2020First generator online
- Operator
- Harvest Ridge Wind FarmEIA operator ID 60719
- Grid
- MISOBalancing authority MISO
- Price nodes
- 1 MISO nodeResource nodes with prices
- Location
- Douglas County, IL39.8319, −88.0723
- EIA plant ID
- 61161EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Harvest Ridge Wind Farm produces
Free · EIA-923Net generation, 2025
667 GWh
667,048 MWh, final
Capacity factor, 2025
37.7%
2024: 42.1%
January to July 2026
466 GWh
Provisional
Range, 2021 to 2025
667.0–765.5
GWh a year. Low 2025, high 2022
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | Not reported | Not reported | 0 of 12 |
| 2020 | 276,482 | Not reported | 6 of 12 |
| 2021 | 693,353 | 39.2% | 12 of 12 |
| 2022 | 765,455 | 43.3% | 12 of 12 |
| 2023 | 691,663 | 39.1% | 12 of 12 |
| 2024 | 747,181 | 42.1% | 12 of 12 |
| 2025 | 667,048 | 37.7% | 12 of 12 |
| 2026 (provisional, partial year) | 466,196 | 45.4% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · MISOEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| GEN01 | Onshore Wind Turbine | 202.0 | July 2020 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Harvest Ridge Wind Farm as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Harvest Ridge Wind Farm and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Harvest Ridge Wind Farm
Questions about Harvest Ridge Wind Farm
How much power does Harvest Ridge Wind Farm produce?
Harvest Ridge Wind Farm reported 667,048 MWh (667 GWh) of net generation in 2025, a 37.7% capacity factor on 202 MW of nameplate capacity. From January to July 2026 it reported 466 GWh, which is provisional.
Where is Harvest Ridge Wind Farm?
Harvest Ridge Wind Farm is in Douglas County, Illinois, at 39.8319, −88.0723. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).
Who operates Harvest Ridge Wind Farm?
EIA-860M for August 2026 lists Harvest Ridge Wind Farm as the operator (EIA operator ID 60719). The operator is not always the owner.
When did Harvest Ridge Wind Farm start operating?
Its first generator began operating in July 2020, according to EIA-860M.
Does InfraMap have power prices for Harvest Ridge Wind Farm?
Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Harvest Ridge Wind Farm, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
- Project names from the USGS U.S. Wind Turbine Database