SolarOperatingSCEG

Otarre Solar Park

Solar power plant in Lexington County, South Carolina. 1.6 MW of nameplate capacity across 1 generator, operated by TIG Sun Energy IV, LLC.

Also known as EIA plant 61699

Analyst: free account, 1 question a day.

Columbia Energy Center (SC)Gaston IIGaston Solar I - SCGunsight Solar, LLCSaluda LexingtonMcMeekinOtarre Solar Park10 km
Open in the map
6 plants within 21 km, from EIA coordinates.

Key facts

Capacity
1.6 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 2017First generator online
Operator
TIG Sun Energy IV, LLCEIA operator ID 61322
Grid
SCEGBalancing authority SCEG
Price nodes
None linkedNo verified ISO node
Location
Lexington County, SC33.9324, −81.0514
EIA plant ID
61699EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Otarre Solar Park produces

Free · EIA-923

Net generation, 2025

2.81 GWh

2,814 MWh, final

Capacity factor, 2025

20.1%

2024: 18.8%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2018 to 2025

2.6–3.0

GWh a year. Low 2024, high 2019

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017292Not reported1 of 12
20182,80920.0%12 of 12
20192,97221.2%12 of 12
20202,81720.0%12 of 12
20212,83620.2%12 of 12
20222,87620.5%12 of 12
20232,75019.6%12 of 12
20242,64818.8%12 of 12
20252,81420.1%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
OTRRESolar Photovoltaic1.6December 2017

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists TIG Sun Energy IV, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Otarre Solar Park and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Otarre Solar Park

Questions about Otarre Solar Park

How much power does Otarre Solar Park produce?

Otarre Solar Park reported 2,814 MWh (2.81 GWh) of net generation in 2025, a 20.1% capacity factor on 1.6 MW of nameplate capacity.

Where is Otarre Solar Park?

Otarre Solar Park is in Lexington County, South Carolina, at 33.9324, −81.0514. It is in the Dominion Energy South Carolina balancing area (SCEG).

Who operates Otarre Solar Park?

EIA-860M for August 2026 lists TIG Sun Energy IV, LLC as the operator (EIA operator ID 61322). The operator is not always the owner.

When did Otarre Solar Park start operating?

Its first generator began operating in December 2017, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page