WindOperatingPJM

Hilltopper Wind Project

Wind power plant in Logan County, Illinois. 185 MW of nameplate capacity across 1 generator, operated by Hilltopper Wind Project, LLC.

Also known as HillTopper · EIA plant 61735

Analyst: free account, 1 question a day.

Mulligan Solar, LLCSugar Creek Wind One LLCTop Hat WindWhitney Hill Wind Power LLCInterstateHilltopper Wind Project10 km
Open in the map
6 plants within 29 km, from EIA coordinates.

Key facts

Capacity
185 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 2018First generator online
Operator
Hilltopper Wind Project, LLCEIA operator ID 61365
Grid
PJMBalancing authority PJM
Price nodes
1 PJM nodeResource nodes with prices
Location
Logan County, IL40.0300, −89.3810
EIA plant ID
61735EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Hilltopper Wind Project produces

Free · EIA-923

Net generation, 2025

474 GWh

473,987 MWh, final

Capacity factor, 2025

29.2%

2024: 32.7%

January to July 2026

330 GWh

Provisional

Range, 2019 to 2025

474.0–621.4

GWh a year. Low 2025, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019591,033Not reported12 of 12
2020541,91233.3%12 of 12
2021559,81434.5%12 of 12
2022621,35938.3%12 of 12
2023547,81433.8%12 of 12
2024532,07232.7%12 of 12
2025473,98729.2%12 of 12
2026 (provisional, partial year)330,13235.1%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · PJM

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
WT1Onshore Wind Turbine185.0December 2018

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Hilltopper Wind Project, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Hilltopper Wind Project and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Hilltopper Wind Project

Questions about Hilltopper Wind Project

How much power does Hilltopper Wind Project produce?

Hilltopper Wind Project reported 473,987 MWh (474 GWh) of net generation in 2025, a 29.2% capacity factor on 185 MW of nameplate capacity. From January to July 2026 it reported 330 GWh, which is provisional.

Where is Hilltopper Wind Project?

Hilltopper Wind Project is in Logan County, Illinois, at 40.0300, −89.3810. It is in the PJM Interconnection, LLC balancing area (PJM).

Who operates Hilltopper Wind Project?

EIA-860M for August 2026 lists Hilltopper Wind Project, LLC as the operator (EIA operator ID 61365). The operator is not always the owner.

When did Hilltopper Wind Project start operating?

Its first generator began operating in December 2018, according to EIA-860M.

Does InfraMap have power prices for Hilltopper Wind Project?

Yes. InfraMap has PJM day-ahead and real-time prices at 1 price node linked to Hilltopper Wind Project, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • PJM day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Project names from the USGS U.S. Wind Turbine Database

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page