TAC-Distributed Energy Resource Hybrid
Solar and wind project in Champaign County, Illinois. 0.5 MW of nameplate capacity across 3 generators, operated by Ameren Illinois.
Also known as EIA plant 61990
This project groups TAC-Distributed Energy Resource Hybrid (EIA 61990). EIA reports them as separate plants.
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 0.5 MWSolar 0.1 · Wind 0.1 · Battery storage 0.3
- Generators
- 3 operatingEIA-860M, August 2026
- Operating since
- March 2017First generator online
- Operator
- Ameren IllinoisEIA operator ID 61576
- Grid
- MISOBalancing authority MISO
- Price nodes
- 1 MISO nodeResource nodes with prices
- Location
- Champaign County, IL40.0898, −88.2436
- EIA plant ID
- 61990EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power TAC-Distributed Energy Resource Hybrid produces
Free · EIA-923Net generation, 2025
294 MWh
294 MWh, final
Capacity factor, 2025
2.9%
2024: 2.9%
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2018 to 2025
266.0–394.0
MWh a year. Low 2023, high 2021
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | 330 | 3.3% | 12 of 12 |
| 2019 | 322 | 3.2% | 12 of 12 |
| 2020 | 298 | 2.9% | 12 of 12 |
| 2021 | 394 | 3.9% | 12 of 12 |
| 2022 | 306 | 3.1% | 12 of 12 |
| 2023 | 266 | 3.0% | 12 of 12 |
| 2024 | 307 | 2.9% | 12 of 12 |
| 2025 | 294 | 2.9% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · MISOEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| BA | Batteries | 0.3 | May 2017 |
| SOLAR | Solar Photovoltaic | 0.1 | March 2017 |
| WIND | Onshore Wind Turbine | 0.1 | March 2017 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Ameren Illinois as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query TAC-Distributed Energy Resource Hybrid and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near TAC-Distributed Energy Resource Hybrid
Questions about TAC-Distributed Energy Resource Hybrid
How much power does TAC-Distributed Energy Resource Hybrid produce?
TAC-Distributed Energy Resource Hybrid reported 294 MWh (294 MWh) of net generation in 2025, a 2.9% capacity factor on 0.5 MW of nameplate capacity.
Where is TAC-Distributed Energy Resource Hybrid?
TAC-Distributed Energy Resource Hybrid is in Champaign County, Illinois, at 40.0898, −88.2436. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).
Who operates TAC-Distributed Energy Resource Hybrid?
EIA-860M for August 2026 lists Ameren Illinois as the operator (EIA operator ID 61576). The operator is not always the owner.
Is TAC-Distributed Energy Resource Hybrid a solar or a wind plant?
Both. Solar capacity totals 0.1 MW and wind capacity totals 0.1 MW, with 0.3 MW of battery storage.
When did TAC-Distributed Energy Resource Hybrid start operating?
Its first generator began operating in March 2017, according to EIA-860M.
Does InfraMap have power prices for TAC-Distributed Energy Resource Hybrid?
Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to TAC-Distributed Energy Resource Hybrid, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page