SolarOperatingPSCO

Pioneer Solar (CO), LLC

Solar power plant in Adams County, Colorado. 80 MW of nameplate capacity across 1 generator, operated by Pioneer Solar (CO), LLC.

Also known as Pioneer Solar · EIA plant 61991

Analyst: free account, 1 question a day.

Victory Solar LLCOak Leaf - CSG Portfolio (OL 44)Pioneer Solar (CO)5 km
Open in the map
6 plants within 11 km, from EIA coordinates.

Key facts

Capacity
80 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
June 2021First generator online
Operator
Pioneer Solar (CO), LLCEIA operator ID 63810
Grid
PSCOBalancing authority PSCO
Price nodes
None linkedNo verified ISO node
Location
Adams County, CO39.7616, −104.4590
EIA plant ID
61991EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Pioneer Solar (CO) produces

Free · EIA-923

Net generation, 2025

180 GWh

179,753 MWh, final

Capacity factor, 2025

25.6%

2024: 28.1%

January to July 2026

109 GWh

Provisional

Range, 2022 to 2025

179.8–204.3

GWh a year. Low 2025, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021146,978Not reported9 of 12
2022204,34929.2%12 of 12
2023179,97325.7%12 of 12
2024197,67728.1%12 of 12
2025179,75325.6%12 of 12
2026 (provisional, partial year)108,80226.7%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
PI-QFSolar Photovoltaic80.0June 2021

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Pioneer Solar (CO), LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Pioneer Solar (CO), LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Pioneer Solar (CO)

Questions about Pioneer Solar (CO)

How much power does Pioneer Solar (CO), LLC produce?

Pioneer Solar (CO), LLC reported 179,753 MWh (180 GWh) of net generation in 2025, a 25.6% capacity factor on 80 MW of nameplate capacity. From January to July 2026 it reported 109 GWh, which is provisional.

Where is Pioneer Solar (CO), LLC?

Pioneer Solar (CO), LLC is in Adams County, Colorado, at 39.7616, −104.4590. It is in the Public Service Company of Colorado balancing area (PSCO).

Who operates Pioneer Solar (CO), LLC?

EIA-860M for August 2026 lists Pioneer Solar (CO), LLC as the operator (EIA operator ID 63810). The operator is not always the owner.

When did Pioneer Solar (CO), LLC start operating?

Its first generator began operating in June 2021, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page