Solar and battery storage project in Calhoun County, South Carolina. 132 MW of nameplate capacity across 2 generators, operated by Lone Star Solar.

Also known as EIA plant 62235

This project groups Lone Star Solar (EIA 62235). EIA reports them as separate plants.

Analyst: free account, 1 question a day.

Cameron SolarCameron Solar IISt. Matthews SolarWatereeBond SolarLone Star Solar10 km
Open in the map
6 plants within 26 km, from EIA coordinates.

Key facts

Capacity
132 MWSolar 66.0 · Battery storage 66.0
Generators
2 operatingEIA-860M, August 2026
Operating since
December 2024First generator online
Operator
Lone Star SolarEIA operator ID 61752
Grid
SCEGBalancing authority SCEG
Price nodes
None linkedNo verified ISO node
Location
Calhoun County, SC33.6488, −80.6391
EIA plant ID
62235EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Lone Star Solar produces

Free · EIA-923

Net generation, 2025

164 GWh

163,965 MWh, final

Capacity factor, 2025

28.6%

2024: Not reported

January to July 2026

112 GWh

Provisional

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
20244,814Not reported1 of 12
2025163,96528.6%12 of 12
2026 (provisional, partial year)112,13233.8%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
49Solar Photovoltaic66.0December 2024
50Batteries66.0December 2024

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Lone Star Solar as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Lone Star Solar and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Lone Star Solar

Questions about Lone Star Solar

How much power does Lone Star Solar produce?

Lone Star Solar reported 163,965 MWh (164 GWh) of net generation in 2025, a 28.6% capacity factor on 132 MW of nameplate capacity. From January to July 2026 it reported 112 GWh, which is provisional.

Where is Lone Star Solar?

Lone Star Solar is in Calhoun County, South Carolina, at 33.6488, −80.6391. It is in the Dominion Energy South Carolina balancing area (SCEG).

Who operates Lone Star Solar?

EIA-860M for August 2026 lists Lone Star Solar as the operator (EIA operator ID 61752). The operator is not always the owner.

Is Lone Star Solar a solar or a battery storage plant?

Both. Solar capacity totals 66 MW and battery storage capacity totals 66 MW.

When did Lone Star Solar start operating?

Its first generator began operating in December 2024, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page