SolarOperatingMISO

Assembly Solar Project

Solar power plant in Shiawassee County, Michigan. 50 MW of nameplate capacity across 1 generator, operated by Assembly Solar I, LLC.

Also known as EIA plant 62422

Analyst: free account, 1 question a day.

Assembly Solar II LLCVenice Resources Gas RecoveryLennon GeneratingColdwater Solar, LLCAssembly Solar Project10 km
Open in the map
6 plants within 16 km, from EIA coordinates.

Key facts

Capacity
50 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 2020First generator online
Operator
Assembly Solar I, LLCEIA operator ID 61949
Grid
MISOBalancing authority MISO
Price nodes
2 MISO nodesResource nodes with prices
Location
Shiawassee County, MI43.0227, −83.9453
EIA plant ID
62422EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Assembly Solar Project produces

Free · EIA-923

Net generation, 2025

99.8 GWh

99,840 MWh, final

Capacity factor, 2025

22.8%

2024: 23.3%

January to July 2026

65.2 GWh

Provisional

Range, 2021 to 2025

99.8–102.3

GWh a year. Low 2025, high 2024

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
20201,599Not reported1 of 12
2021101,80723.2%12 of 12
2022101,45823.2%12 of 12
2023100,01522.8%12 of 12
2024102,32523.3%12 of 12
202599,84022.8%12 of 12
2026 (provisional, partial year)65,17825.6%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
ASP01Solar Photovoltaic50.0December 2020

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Assembly Solar I, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Assembly Solar Project and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Assembly Solar Project

Questions about Assembly Solar Project

How much power does Assembly Solar Project produce?

Assembly Solar Project reported 99,840 MWh (99.8 GWh) of net generation in 2025, a 22.8% capacity factor on 50 MW of nameplate capacity. From January to July 2026 it reported 65.2 GWh, which is provisional.

Where is Assembly Solar Project?

Assembly Solar Project is in Shiawassee County, Michigan, at 43.0227, −83.9453. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Assembly Solar Project?

EIA-860M for August 2026 lists Assembly Solar I, LLC as the operator (EIA operator ID 61949). The operator is not always the owner.

When did Assembly Solar Project start operating?

Its first generator began operating in December 2020, according to EIA-860M.

Does InfraMap have power prices for Assembly Solar Project?

Yes. InfraMap has MISO day-ahead and real-time prices at 2 price nodes linked to Assembly Solar Project, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page