WindOperatingISO-NE

Jiminy Peak Wind QF

Wind power plant in Berkshire County, Massachusetts. 1.5 MW of nameplate capacity across 1 generator, operated by Jiminy Peak Mountain Resort, LLC.

Also known as EIA plant 62570

Analyst: free account, 1 question a day.

Nexamp Peak CSGBerkshire Wind Power ProjectSaddleback SolarSkyline SolarEast Acres Solar NG, LLCPartridge SolarJiminy Peak Wind QF2 km
Open in the map
6 plants within 8.8 km, from EIA coordinates.

Key facts

Capacity
1.5 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
August 2007First generator online
Operator
Jiminy Peak Mountain Resort, LLCEIA operator ID 62069
Grid
ISO-NEBalancing authority ISNE
Price nodes
None linkedNo verified ISO node
Location
Berkshire County, MA42.5437, −73.2926
EIA plant ID
62570EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Jiminy Peak Wind QF produces

Free · EIA-923

Net generation, 2025

2 MWh

2 MWh, final

Capacity factor, 2025

0.0%

2024: 0.0%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2019 to 2025

0.0–2.0

MWh a year. Low 2023, high 2020

Annual net generation, MWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
201910.0%12 of 12
202020.0%12 of 12
202120.0%12 of 12
202210.0%12 of 12
202300.0%12 of 12
202400.0%12 of 12
202520.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
32651Onshore Wind Turbine1.5August 2007

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Jiminy Peak Mountain Resort, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Jiminy Peak Wind QF and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Jiminy Peak Wind QF

Questions about Jiminy Peak Wind QF

How much power does Jiminy Peak Wind QF produce?

Jiminy Peak Wind QF reported 2 MWh (2 MWh) of net generation in 2025, a 0.0% capacity factor on 1.5 MW of nameplate capacity.

Where is Jiminy Peak Wind QF?

Jiminy Peak Wind QF is in Berkshire County, Massachusetts, at 42.5437, −73.2926. It is in the ISO New England Inc. balancing area (ISNE).

Who operates Jiminy Peak Wind QF?

EIA-860M for August 2026 lists Jiminy Peak Mountain Resort, LLC as the operator (EIA operator ID 62069). The operator is not always the owner.

When did Jiminy Peak Wind QF start operating?

Its first generator began operating in August 2007, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page