Quitman Solar
Solar power plant in Brooks County, Georgia. 150 MW of nameplate capacity across 1 generator, operated by Quitman Solar, LLC.
Also known as EIA plant 62584
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 150 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- December 2019First generator online
- Operator
- Quitman Solar, LLCEIA operator ID 61910
- Grid
- SOCOBalancing authority SOCO
- Price nodes
- None linkedNo verified ISO node
- Location
- Brooks County, GA30.8490, −83.6433
- EIA plant ID
- 62584EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Quitman Solar produces
Free · EIA-923Net generation, 2025
320 GWh
320,208 MWh, final
Capacity factor, 2025
24.4%
2024: 25.1%
January to July 2026
208 GWh
Provisional
Range, 2020 to 2025
320.2–354.5
GWh a year. Low 2025, high 2020
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | 19,146 | Not reported | 1 of 12 |
| 2020 | 354,506 | 26.9% | 12 of 12 |
| 2021 | 335,033 | 25.5% | 12 of 12 |
| 2022 | 352,578 | 26.8% | 12 of 12 |
| 2023 | 345,062 | 26.3% | 12 of 12 |
| 2024 | 330,486 | 25.1% | 12 of 12 |
| 2025 | 320,208 | 24.4% | 12 of 12 |
| 2026 (provisional, partial year) | 207,957 | 27.2% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| QUITM | Solar Photovoltaic | 150.0 | December 2019 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Quitman Solar, LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Quitman Solar and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Quitman Solar
Questions about Quitman Solar
How much power does Quitman Solar produce?
Quitman Solar reported 320,208 MWh (320 GWh) of net generation in 2025, a 24.4% capacity factor on 150 MW of nameplate capacity. From January to July 2026 it reported 208 GWh, which is provisional.
Where is Quitman Solar?
Quitman Solar is in Brooks County, Georgia, at 30.8490, −83.6433. It is in the Southern Company Services, Inc. - Trans balancing area (SOCO).
Who operates Quitman Solar?
EIA-860M for August 2026 lists Quitman Solar, LLC as the operator (EIA operator ID 61910). The operator is not always the owner.
When did Quitman Solar start operating?
Its first generator began operating in December 2019, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page