Elora Solar

Solar power plant in Lincoln County, Tennessee. 150 MW of nameplate capacity across 1 generator, operated by Elora Solar.

Also known as EIA plant 63719

Analyst: free account, 1 question a day.

Tims FordTAI Huntsville Solar HybridCumblerland Land Holdings, LLCRedstone Arsenal HybridSR Bell BuckleElora Solar25 km
Open in the map
5 plants within 58 km, from EIA coordinates.

Key facts

Capacity
150 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
March 2022First generator online
Operator
Elora SolarEIA operator ID 63418
Grid
TVABalancing authority TVA
Price nodes
None linkedNo verified ISO node
Location
Lincoln County, TN35.0600, −86.3400
EIA plant ID
63719EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Elora Solar produces

Free · EIA-923

Net generation, 2025

316 GWh

316,033 MWh, final

Capacity factor, 2025

24.1%

2024: 23.2%

January to July 2026

207 GWh

Provisional

Range, 2023 to 2025

305.9–347.4

GWh a year. Low 2024, high 2023

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022307,891Not reported10 of 12
2023347,41326.4%12 of 12
2024305,85323.2%12 of 12
2025316,03324.1%12 of 12
2026 (provisional, partial year)207,06627.1%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
ELOSolar Photovoltaic150.0March 2022

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Elora Solar as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Elora Solar and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Elora Solar

Questions about Elora Solar

How much power does Elora Solar produce?

Elora Solar reported 316,033 MWh (316 GWh) of net generation in 2025, a 24.1% capacity factor on 150 MW of nameplate capacity. From January to July 2026 it reported 207 GWh, which is provisional.

Where is Elora Solar?

Elora Solar is in Lincoln County, Tennessee, at 35.0600, −86.3400. It is in the Tennessee Valley Authority balancing area (TVA).

Who operates Elora Solar?

EIA-860M for August 2026 lists Elora Solar as the operator (EIA operator ID 63418). The operator is not always the owner.

When did Elora Solar start operating?

Its first generator began operating in March 2022, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page