SolarOperatingSOCO

Lowndes Tycor Farms

Solar power plant in Lowndes County, Georgia. 2.3 MW of nameplate capacity across 1 generator, operated by Safari Energy, LLC.

Also known as Lowndes Tycor Farms Solar · EIA plant 64279

Analyst: free account, 1 question a day.

Jennings Energy Storage FacilityValdosta (Terraform)Lowndes IDALowndes Tycor Farms10 km
Open in the map
6 plants within 23 km, from EIA coordinates.

Key facts

Capacity
2.3 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
May 2020First generator online
Operator
Safari Energy, LLCEIA operator ID 63640
Grid
SOCOBalancing authority SOCO
Price nodes
None linkedNo verified ISO node
Location
Lowndes County, GA30.6882, −83.1672
EIA plant ID
64279EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Lowndes Tycor Farms produces

Free · EIA-923

Net generation, 2025

5.12 GWh

5,121 MWh, final

Capacity factor, 2025

25.4%

2024: 22.7%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2021 to 2025

4.5–5.1

GWh a year. Low 2022, high 2025

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
20203,161Not reported8 of 12
20214,81823.9%12 of 12
20224,54122.5%12 of 12
20234,82323.9%12 of 12
20244,57722.7%12 of 12
20255,12125.4%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
LTFSolar Photovoltaic2.3May 2020

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Safari Energy, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Lowndes Tycor Farms and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Lowndes Tycor Farms

More plants operated by Safari Energy, LLC

Questions about Lowndes Tycor Farms

How much power does Lowndes Tycor Farms produce?

Lowndes Tycor Farms reported 5,121 MWh (5.12 GWh) of net generation in 2025, a 25.4% capacity factor on 2.3 MW of nameplate capacity.

Where is Lowndes Tycor Farms?

Lowndes Tycor Farms is in Lowndes County, Georgia, at 30.6882, −83.1672. It is in the Southern Company Services, Inc. - Trans balancing area (SOCO).

Who operates Lowndes Tycor Farms?

EIA-860M for August 2026 lists Safari Energy, LLC as the operator (EIA operator ID 63640). The operator is not always the owner.

When did Lowndes Tycor Farms start operating?

Its first generator began operating in May 2020, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page