SolarOperatingERCOT

Concho Valley Solar, LLC

Solar power plant in Tom Green County, Texas. 172.8 MW of nameplate capacity across 1 generator, operated by Concho Valley Solar, LLC.

Also known as EIA plant 65793

Analyst: free account, 1 question a day.

Cactus Flats Wind Energy ProjectNorton Solar FarmMaverick Creek WindLive Oak Wind ProjectGalloway 2 Solar FarmConcho Valley Solar25 km
Open in the map
6 plants within 43 km, from EIA coordinates.

Key facts

Capacity
172.8 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
May 2023First generator online
Operator
Concho Valley Solar, LLCEIA operator ID 65055
Grid
ERCOTBalancing authority ERCO
Price nodes
1 ERCOT nodeResource nodes with prices
Location
Tom Green County, TX31.2140, −100.2550
EIA plant ID
65793EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Concho Valley Solar produces

Free · EIA-923

Net generation, 2025

304 GWh

303,594 MWh, final

Capacity factor, 2025

20.1%

2024: 19.4%

January to July 2026

149 GWh

Provisional

Range, 2023 to 2025

295.2–336.1

GWh a year. Low 2024, high 2023

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
202293,922Not reported4 of 12
2023336,108Not reported12 of 12
2024295,15119.4%12 of 12
2025303,59420.1%12 of 12
2026 (provisional, partial year)148,81316.9%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
CVSSolar Photovoltaic172.8May 2023

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Concho Valley Solar, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Concho Valley Solar, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Concho Valley Solar

Questions about Concho Valley Solar

How much power does Concho Valley Solar, LLC produce?

Concho Valley Solar, LLC reported 303,594 MWh (304 GWh) of net generation in 2025, a 20.1% capacity factor on 172.8 MW of nameplate capacity. From January to July 2026 it reported 149 GWh, which is provisional.

Where is Concho Valley Solar, LLC?

Concho Valley Solar, LLC is in Tom Green County, Texas, at 31.2140, −100.2550. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Concho Valley Solar, LLC?

EIA-860M for August 2026 lists Concho Valley Solar, LLC as the operator (EIA operator ID 65055). The operator is not always the owner.

When did Concho Valley Solar, LLC start operating?

Its first generator began operating in May 2023, according to EIA-860M.

Does InfraMap have power prices for Concho Valley Solar, LLC?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 1 price node linked to Concho Valley Solar, LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page