Seven Cowboy Wind Project, LLC
Wind power plant in Washita County, Oklahoma. 301.7 MW of nameplate capacity across 1 generator, operated by Seven Cowboy Wind Project, LLC.
Also known as Seven Cowboy Wind Project · Seven Cowboy · EIA plant 65971
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 301.7 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- March 2023First generator online
- Operator
- Seven Cowboy Wind Project, LLCEIA operator ID 65148
- Grid
- SPPBalancing authority SWPP
- Price nodes
- 1 SPP nodeResource nodes with prices
- Location
- Washita County, OK35.2183, −99.1040
- EIA plant ID
- 65971EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Seven Cowboy Wind Project produces
Free · EIA-923Net generation, 2025
1.17 TWh
1,171,818 MWh, final
Capacity factor, 2025
44.3%
2024: 37.4%
January to July 2026
788 GWh
Provisional
Range, 2024 to 2025
1.0–1.2
TWh a year. Low 2024, high 2025
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | Not reported | Not reported | 0 of 12 |
| 2020 | Not reported | Not reported | 0 of 12 |
| 2021 | Not reported | Not reported | 0 of 12 |
| 2022 | Not reported | Not reported | 0 of 12 |
| 2023 | 751,370 | Not reported | 11 of 12 |
| 2024 | 989,888 | 37.4% | 12 of 12 |
| 2025 | 1,171,818 | 44.3% | 12 of 12 |
| 2026 (provisional, partial year) | 787,929 | 51.3% | 7 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free account · SPPEmissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| WT1 | Onshore Wind Turbine | 301.7 | March 2023 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Seven Cowboy Wind Project, LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Seven Cowboy Wind Project, LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Seven Cowboy Wind Project
Questions about Seven Cowboy Wind Project
How much power does Seven Cowboy Wind Project, LLC produce?
Seven Cowboy Wind Project, LLC reported 1,171,818 MWh (1.17 TWh) of net generation in 2025, a 44.3% capacity factor on 301.7 MW of nameplate capacity. From January to July 2026 it reported 788 GWh, which is provisional.
Where is Seven Cowboy Wind Project, LLC?
Seven Cowboy Wind Project, LLC is in Washita County, Oklahoma, at 35.2183, −99.1040. It is in the Southwest Power Pool balancing area (SWPP).
Who operates Seven Cowboy Wind Project, LLC?
EIA-860M for August 2026 lists Seven Cowboy Wind Project, LLC as the operator (EIA operator ID 65148). The operator is not always the owner.
When did Seven Cowboy Wind Project, LLC start operating?
Its first generator began operating in March 2023, according to EIA-860M.
Does InfraMap have power prices for Seven Cowboy Wind Project, LLC?
Yes. InfraMap has SPP day-ahead and real-time prices at 1 price node linked to Seven Cowboy Wind Project, LLC, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- SPP day-ahead and real-time prices; node and hub assignments as of 2026-10-05
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
- Project names from the USGS U.S. Wind Turbine Database
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page