Ameresco HCE Solar LLC
Solar power plant in Garfield County, Colorado. 4.5 MW of nameplate capacity across 1 generator, operated by Ameresco HCE Solar LLC.
Also known as Ameresco HCE Solar · Ameresco HCE Solar, LLC · EIA plant 66271
Analyst: free account, 1 question a day.
Key facts
- Capacity
- 4.5 MWNameplate
- Generators
- 1 operatingEIA-860M, August 2026
- Operating since
- August 2023First generator online
- Operator
- Ameresco HCE Solar LLCEIA operator ID 65395
- Grid
- PSCOBalancing authority PSCO
- Price nodes
- None linkedNo verified ISO node
- Location
- Garfield County, CO39.4665, −107.2348
- EIA plant ID
- 66271EIA plant page
Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.
How much power Ameresco HCE Solar produces
Free · EIA-923Net generation, 2025
9.37 GWh
9,371 MWh, final
Capacity factor, 2025
23.8%
2024: Not reported
January to July 2026
Not reported
Provisional. 0 of 7 months reported
Range, 2024 to 2025
8.6–9.4
GWh a year. Low 2024, high 2025
| Year | Net generation, MWh | Capacity factor | Months reported |
|---|---|---|---|
| 2000 | Not reported | Not reported | 0 of 12 |
| 2001 | Not reported | Not reported | 0 of 12 |
| 2002 | Not reported | Not reported | 0 of 12 |
| 2003 | Not reported | Not reported | 0 of 12 |
| 2004 | Not reported | Not reported | 0 of 12 |
| 2005 | Not reported | Not reported | 0 of 12 |
| 2006 | Not reported | Not reported | 0 of 12 |
| 2007 | Not reported | Not reported | 0 of 12 |
| 2008 | Not reported | Not reported | 0 of 12 |
| 2009 | Not reported | Not reported | 0 of 12 |
| 2010 | Not reported | Not reported | 0 of 12 |
| 2011 | Not reported | Not reported | 0 of 12 |
| 2012 | Not reported | Not reported | 0 of 12 |
| 2013 | Not reported | Not reported | 0 of 12 |
| 2014 | Not reported | Not reported | 0 of 12 |
| 2015 | Not reported | Not reported | 0 of 12 |
| 2016 | Not reported | Not reported | 0 of 12 |
| 2017 | Not reported | Not reported | 0 of 12 |
| 2018 | Not reported | Not reported | 0 of 12 |
| 2019 | Not reported | Not reported | 0 of 12 |
| 2020 | Not reported | Not reported | 0 of 12 |
| 2021 | Not reported | Not reported | 0 of 12 |
| 2022 | Not reported | Not reported | 0 of 12 |
| 2023 | 2,458 | Not reported | 5 of 12 |
| 2024 | 8,634 | Not reported | 12 of 12 |
| 2025 | 9,371 | 23.8% | 12 of 12 |
| 2026 (provisional, partial year) | Not reported | Not reported | 0 of 7 |
* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.
Power prices and basis
Free accountNo verified ISO price node is linked to this plant, or its price history could not load.
Emissions
Free · EPA CAMPDNo EPA emissions units are linked to this plant.
Water use
Free · EIA-923 cooling, USGSNo EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.
Generators
Free · EIA-860M| Generator | Technology | Nameplate MW | Online since |
|---|---|---|---|
| HCEPV | Solar Photovoltaic | 4.5 | August 2023 |
Ownership and offtake
ProOwnership and offtake are part of Pro
Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Ameresco HCE Solar LLC as the operator, which is not always the owner.
Modeled data
ProPro adds modeled values for this plant. Everything above stays free.
Modeled curtailment
A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.
Expected vs reported generation
Monthly modeled expected output and physical potential next to EIA-923 reported output.
300 analyst questions a month, plus MCP
Query Ameresco HCE Solar LLC and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.
Power plants near Ameresco HCE Solar
Questions about Ameresco HCE Solar
How much power does Ameresco HCE Solar LLC produce?
Ameresco HCE Solar LLC reported 9,371 MWh (9.37 GWh) of net generation in 2025, a 23.8% capacity factor on 4.5 MW of nameplate capacity.
Where is Ameresco HCE Solar LLC?
Ameresco HCE Solar LLC is in Garfield County, Colorado, at 39.4665, −107.2348. It is in the Public Service Company of Colorado balancing area (PSCO).
Who operates Ameresco HCE Solar LLC?
EIA-860M for August 2026 lists Ameresco HCE Solar LLC as the operator (EIA operator ID 65395). The operator is not always the owner.
When did Ameresco HCE Solar LLC start operating?
Its first generator began operating in August 2023, according to EIA-860M.
Sources
- EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
- EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
- Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)
- Project names from the USGS U.S. Large-Scale Solar Photovoltaic Database
Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page