Solar power plant in Kiowa County, Oklahoma. 120 MW of nameplate capacity across 1 generator, operated by North Fork Solar Project, LLC.

Also known as EIA plant 66866

Analyst: free account, 1 question a day.

Blue Canyon Windpower IIBlue Canyon Windpower VI LLCBlue Summit Wind LLCNorth Fork Solar Project25 km
Open in the map
6 plants within 51 km, from EIA coordinates.

Key facts

Capacity
120 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
May 2024First generator online
Operator
North Fork Solar Project, LLCEIA operator ID 65796
Grid
SPPBalancing authority SWPP
Price nodes
1 SPP nodeResource nodes with prices
Location
Kiowa County, OK34.6178, −98.9826
EIA plant ID
66866EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power North Fork Solar Project produces

Free · EIA-923

Net generation, 2025

294 GWh

294,342 MWh, final

Capacity factor, 2025

28.0%

2024: Not reported

January to July 2026

196 GWh

Provisional

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
2001Not reportedNot reported0 of 12
2002Not reportedNot reported0 of 12
2003Not reportedNot reported0 of 12
2004Not reportedNot reported0 of 12
2005Not reportedNot reported0 of 12
2006Not reportedNot reported0 of 12
2007Not reportedNot reported0 of 12
2008Not reportedNot reported0 of 12
2009Not reportedNot reported0 of 12
2010Not reportedNot reported0 of 12
2011Not reportedNot reported0 of 12
2012Not reportedNot reported0 of 12
2013Not reportedNot reported0 of 12
2014Not reportedNot reported0 of 12
2015Not reportedNot reported0 of 12
2016Not reportedNot reported0 of 12
2017Not reportedNot reported0 of 12
2018Not reportedNot reported0 of 12
2019Not reportedNot reported0 of 12
2020Not reportedNot reported0 of 12
2021Not reportedNot reported0 of 12
2022Not reportedNot reported0 of 12
2023Not reportedNot reported0 of 12
2024215,183Not reported8 of 12
2025294,34228.0%12 of 12
2026 (provisional, partial year)195,66432.0%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · SPP

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
NFORKSolar Photovoltaic120.0May 2024

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists North Fork Solar Project, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query North Fork Solar Project and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near North Fork Solar Project

Questions about North Fork Solar Project

How much power does North Fork Solar Project produce?

North Fork Solar Project reported 294,342 MWh (294 GWh) of net generation in 2025, a 28.0% capacity factor on 120 MW of nameplate capacity. From January to July 2026 it reported 196 GWh, which is provisional.

Where is North Fork Solar Project?

North Fork Solar Project is in Kiowa County, Oklahoma, at 34.6178, −98.9826. It is in the Southwest Power Pool balancing area (SWPP).

Who operates North Fork Solar Project?

EIA-860M for August 2026 lists North Fork Solar Project, LLC as the operator (EIA operator ID 65796). The operator is not always the owner.

When did North Fork Solar Project start operating?

Its first generator began operating in May 2024, according to EIA-860M.

Does InfraMap have power prices for North Fork Solar Project?

Yes. InfraMap has SPP day-ahead and real-time prices at 1 price node linked to North Fork Solar Project, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • SPP day-ahead and real-time prices; node and hub assignments as of 2026-10-05