Major Oak Power

Coal power plant in Robertson County, Texas. 349.2 MW of nameplate capacity across 2 generators, operated by Major Oak Power, LLC.

Also known as Twin Oaks Power Station · TNP One · EIA plant 7030

Analyst: free account, 1 question a day.

Tidwell Prairie Storage 1Oak Grove (TX)Orion II Solar ProjectTX11 Republic Road StorageMarlin SolarOrion I Solar ProjectMajor Oak Power10 km
Open in the map
6 plants within 31 km, from EIA coordinates.

Key facts

Capacity
349.2 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
September 1990First generator online
Operator
Major Oak Power, LLCEIA operator ID 56598
Grid
ERCOTBalancing authority ERCO
Price nodes
2 ERCOT nodesResource nodes with prices
Location
Robertson County, TX31.0919, −96.6950
EIA plant ID
7030EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Major Oak Power produces

Free · EIA-923

Net generation, 2025

2.23 TWh

2,230,399 MWh, final

Capacity factor, 2025

72.9%

2024: 67.2%

January to July 2026

1.24 TWh

Provisional

Range, 2015 to 2025

2.1–2.5

TWh a year. Low 2024, high 2016

Annual net generation, TWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20002,215,215Not reported12 of 12
20012,349,700Not reported12 of 12
20022,472,216Not reported12 of 12
20032,475,295Not reported12 of 12
20042,342,321Not reported12 of 12
20052,490,416Not reported12 of 12
20062,351,664Not reported12 of 12
20072,316,023Not reported12 of 12
20082,411,517Not reported12 of 12
20092,180,212Not reported12 of 12
20102,386,68378.0%12 of 12
20112,286,05674.7%12 of 12
20121,513,73649.3%12 of 12
20132,068,24867.6%12 of 12
20141,659,99880.8%8 of 12
20152,434,41379.6%12 of 12
20162,467,58980.4%12 of 12
20172,383,54777.9%12 of 12
20182,457,77980.3%12 of 12
20192,413,92478.9%12 of 12
20202,385,51577.8%12 of 12
20212,337,74876.4%12 of 12
20222,442,93279.9%12 of 12
20232,319,41675.8%12 of 12
20242,061,10167.2%12 of 12
20252,230,39972.9%12 of 12
2026 (provisional, partial year)1,236,94669.6%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ERCOT

Emissions

Free · EPA CAMPD

CO₂, 2025

2.82M

US short tons. 2024: 2.61M

SO₂, 2025

1,966

US short tons

NOx, 2025

1,992

US short tons

CO₂ per MWh, calculated

1.26 t

About 2,527 lb per MWh

2 of 2 EPA units reported CO₂ in 2025 (U1, U2), matched to EIA plant 7030 through the EPA–EIA crosswalk. The per-MWh rate is EPA CO₂ divided by EIA-923 net generation. The two reporting boundaries can differ.

Water use

Free · EIA-923 cooling, USGS

Withdrawal, 2024

1,401

million gallons

Consumption, 2024

1,073

million gallons

Source

Wells

Ground, Fresh. Induced-draft tower

Watershed stress

Moderate · 0.521

USGS SUI, HUC12 South Walnut Creek

24 of 24 cooling months report withdrawal. Groundwater user; SUI describes surface water and is context only. Blank volumes are unreported, not zero.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Conventional Steam Coal174.6September 1990
2Conventional Steam Coal174.6October 1991

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Major Oak Power, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Major Oak Power and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Major Oak Power

Questions about Major Oak Power

How much power does Major Oak Power produce?

Major Oak Power reported 2,230,399 MWh (2.23 TWh) of net generation in 2025, a 72.9% capacity factor on 349.2 MW of nameplate capacity. From January to July 2026 it reported 1.24 TWh, which is provisional.

Where is Major Oak Power?

Major Oak Power is in Robertson County, Texas, at 31.0919, −96.6950. It is in the Electric Reliability Council of Texas, Inc. balancing area (ERCO).

Who operates Major Oak Power?

EIA-860M for August 2026 lists Major Oak Power, LLC as the operator (EIA operator ID 56598). The operator is not always the owner.

When did Major Oak Power start operating?

Its first generator began operating in September 1990, according to EIA-860M.

Does InfraMap have power prices for Major Oak Power?

Yes. InfraMap has ERCOT day-ahead and real-time prices at 2 price nodes linked to Major Oak Power, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • EPA CAMPD annual emissions through the EPA–EIA crosswalk, 1995 to 2025
  • ERCOT day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • EIA-923 cooling water 2024 and the USGS surface water supply and use index, Water years 2010-2020 (Oct 2009 to Sep 2020), mean of monthly values
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page