Key facts

Capacity
3.4 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
February 1985First generator online
Operator
City of Lakefield - (MN)EIA operator ID 10622
Grid
MISOBalancing authority MISO
Price nodes
1 MISO nodeResource nodes with prices
Location
Jackson County, MN43.6742, −95.1706
EIA plant ID
7415EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Lakefield Utilities produces

Free · EIA-923

Net generation, 2025

11 MWh

11 MWh, final

Capacity factor, 2025

0.0%

2024: 0.0%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

6.0–24.0

MWh a year. Low 2024, high 2021

Annual net generation, MWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20000Not reported12 of 12
200136Not reported12 of 12
200218Not reported12 of 12
20039Not reported12 of 12
200431Not reported12 of 12
200528Not reported12 of 12
200615Not reported12 of 12
200715Not reported12 of 12
200812Not reported12 of 12
200911Not reported12 of 12
2010120.0%12 of 12
2011130.0%12 of 12
2012170.1%12 of 12
2013260.1%12 of 12
2014130.0%12 of 12
2015130.0%12 of 12
2016170.1%12 of 12
2017110.0%12 of 12
2018230.1%12 of 12
2019130.0%12 of 12
2020100.0%12 of 12
2021240.1%12 of 12
2022200.1%12 of 12
2023130.0%12 of 12
202460.0%12 of 12
2025110.0%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
5Petroleum Liquids1.2February 1985
6Petroleum Liquids2.2June 2003

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists City of Lakefield - (MN) as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Lakefield Utilities and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Lakefield Utilities

Questions about Lakefield Utilities

How much power does Lakefield Utilities produce?

Lakefield Utilities reported 11 MWh (11 MWh) of net generation in 2025, a 0.0% capacity factor on 3.4 MW of nameplate capacity.

Where is Lakefield Utilities?

Lakefield Utilities is in Jackson County, Minnesota, at 43.6742, −95.1706. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Lakefield Utilities?

EIA-860M for August 2026 lists City of Lakefield - (MN) as the operator (EIA operator ID 10622). The operator is not always the owner.

When did Lakefield Utilities start operating?

Its first generator began operating in February 1985, according to EIA-860M.

Does InfraMap have power prices for Lakefield Utilities?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Lakefield Utilities, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page