Key facts

Capacity
11 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
June 1999First generator online
Operator
Madison Gas & Electric CoEIA operator ID 11479
Grid
MISOBalancing authority MISO
Price nodes
1 MISO nodeResource nodes with prices
Location
Kewaunee County, WI44.6694, −87.6333
EIA plant ID
7886EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Wind Turbine produces

Free · EIA-923

Net generation, 2025

12.0 GWh

12,018 MWh, final

Capacity factor, 2025

12.5%

2024: 13.9%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

12.0–17.8

GWh a year. Low 2025, high 2022

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
20002,213Not reported12 of 12
200121,868Not reported12 of 12
200222,937Not reported12 of 12
200321,228Not reported12 of 12
200421,809Not reported12 of 12
200518,784Not reported12 of 12
200619,264Not reported12 of 12
200723,322Not reported12 of 12
200820,929Not reported12 of 12
200920,149Not reported12 of 12
201018,76619.5%12 of 12
201119,51320.3%12 of 12
201220,27721.0%12 of 12
201319,01719.7%12 of 12
201417,71718.4%12 of 12
201516,75817.4%12 of 12
201616,09916.7%12 of 12
201716,46017.1%12 of 12
201815,40416.0%12 of 12
201915,97716.6%12 of 12
202017,54318.2%12 of 12
202114,91115.5%12 of 12
202217,82618.5%12 of 12
202315,00915.6%12 of 12
202413,39713.9%12 of 12
202512,01812.5%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · MISO

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
1Onshore Wind Turbine11.0June 1999

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Madison Gas & Electric Co as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Modeled curtailment

A range, not one number. The lower bound counts hours inside the production tax credit window; the upper bound is the no-credit case.

Modeled

Expected vs reported generation

Monthly modeled expected output and physical potential next to EIA-923 reported output.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Wind Turbine and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Wind Turbine

More plants operated by Madison Gas & Electric Co

Questions about Wind Turbine

How much power does Wind Turbine produce?

Wind Turbine reported 12,018 MWh (12.0 GWh) of net generation in 2025, a 12.5% capacity factor on 11 MW of nameplate capacity.

Where is Wind Turbine?

Wind Turbine is in Kewaunee County, Wisconsin, at 44.6694, −87.6333. It is in the Midcontinent Independent Transmission System Operator, Inc.. balancing area (MISO).

Who operates Wind Turbine?

EIA-860M for August 2026 lists Madison Gas & Electric Co as the operator (EIA operator ID 11479). The operator is not always the owner.

When did Wind Turbine start operating?

Its first generator began operating in June 1999, according to EIA-860M.

Does InfraMap have power prices for Wind Turbine?

Yes. InfraMap has MISO day-ahead and real-time prices at 1 price node linked to Wind Turbine, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • MISO day-ahead and real-time prices; node and hub assignments as of 2026-10-05
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page