HydroOperatingISO-NE

Lockwood Hydroelectric Facility

Hydro power plant in Kennebec County, Maine. 7.2 MW of nameplate capacity across 7 generators, operated by Merimil Ltd Partnership.

Also known as EIA plant 10066

Analyst: free account, 1 question a day.

Hydro Kennebec ProjectMessalonskee 5Cenergy - Waterville (CSG)Winslow PV - BD Solar 2 LLCSolar Mule, LLCWinslow PV, LLCLockwood Hydroelectri…2 km
Open in the map
6 plants within 4.2 km, from EIA coordinates.

Key facts

Capacity
7.2 MWNameplate
Generators
7 operatingEIA-860M, August 2026
Operating since
October 1985First generator online
Operator
Merimil Ltd PartnershipEIA operator ID 12401
Grid
ISO-NEBalancing authority ISNE
Price nodes
1 ISONE nodeResource nodes with prices
Location
Kennebec County, ME44.5467, −69.6292
EIA plant ID
10066EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Lockwood Hydroelectric Facility produces

Free · EIA-923

Net generation, 2025

13.0 GWh

12,964 MWh, final

Capacity factor, 2025

20.6%

2024: 21.5%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

13.0–30.6

GWh a year. Low 2025, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
200190,658Not reported12 of 12
200232,103Not reported12 of 12
200329,350Not reported12 of 12
200432,190Not reported12 of 12
200531,488Not reported12 of 12
200642,166Not reported12 of 12
200732,185Not reported12 of 12
200834,147Not reported12 of 12
200935,969Not reported12 of 12
201032,37151.3%12 of 12
201133,24952.7%12 of 12
201237,39559.1%12 of 12
201333,44153.0%12 of 12
201430,52148.4%12 of 12
201527,44043.5%12 of 12
201630,62148.4%12 of 12
201727,98244.4%12 of 12
201827,59943.8%12 of 12
201928,57045.3%12 of 12
202027,23943.1%12 of 12
202119,86931.5%12 of 12
202219,89531.5%12 of 12
202323,69437.6%12 of 12
202413,57221.5%12 of 12
202512,96420.6%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account · ISONE

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Conventional Hydroelectric0.8October 1985
GEN2Conventional Hydroelectric0.8October 1985
GEN3Conventional Hydroelectric0.8October 1985
GEN4Conventional Hydroelectric0.8October 1985
GEN5Conventional Hydroelectric0.8October 1985
GEN6Conventional Hydroelectric0.8October 1985
GEN7Conventional Hydroelectric2.4October 1988

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Merimil Ltd Partnership as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Lockwood Hydroelectric Facility and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Lockwood Hydroelectric Facility

Questions about Lockwood Hydroelectric Facility

How much power does Lockwood Hydroelectric Facility produce?

Lockwood Hydroelectric Facility reported 12,964 MWh (13.0 GWh) of net generation in 2025, a 20.6% capacity factor on 7.2 MW of nameplate capacity.

Where is Lockwood Hydroelectric Facility?

Lockwood Hydroelectric Facility is in Kennebec County, Maine, at 44.5467, −69.6292. It is in the ISO New England Inc. balancing area (ISNE).

Who operates Lockwood Hydroelectric Facility?

EIA-860M for August 2026 lists Merimil Ltd Partnership as the operator (EIA operator ID 12401). The operator is not always the owner.

When did Lockwood Hydroelectric Facility start operating?

Its first generator began operating in October 1985, according to EIA-860M.

Does InfraMap have power prices for Lockwood Hydroelectric Facility?

Yes. InfraMap has ISONE day-ahead and real-time prices at 1 price node linked to Lockwood Hydroelectric Facility, with the hub price and node-to-hub basis. Prices are free with an InfraMap account; pricing node names are part of InfraMap Pro.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • ISONE day-ahead and real-time prices; node and hub assignments as of 2026-10-05

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page