HydroOperatingCPLE

Metropolitan Sewerage District

Hydro power plant in Buncombe County, North Carolina. 1.6 MW of nameplate capacity across 2 generators, operated by Metropolitan Sewerage District.

Also known as Metropolitan Sewerage District Power Plant · EIA plant 10181

Analyst: free account, 1 question a day.

Biltmore Solar FieldsMarshall DamAsheville-Rock Hill BatteryMetropolitan Sewerage…5 km
Open in the map
5 plants within 14 km, from EIA coordinates.

Key facts

Capacity
1.6 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
September 1988First generator online
Operator
Metropolitan Sewerage DistrictEIA operator ID 12374
Grid
CPLEBalancing authority CPLE
Price nodes
None linkedNo verified ISO node
Location
Buncombe County, NC35.6497, −82.5992
EIA plant ID
10181EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Metropolitan Sewerage District produces

Free · EIA-923

Net generation, 2025

3.49 GWh

3,494 MWh, final

Capacity factor, 2025

16.6%

2024: 29.1%

January to July 2026

2.79 GWh

Provisional

Range, 2015 to 2025

3.5–8.6

GWh a year. Low 2025, high 2016

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
20017Not reported12 of 12
20026,522Not reported12 of 12
20031,135Not reported12 of 12
200412,447Not reported12 of 12
200512,621Not reported12 of 12
20068,046Not reported12 of 12
20073,698Not reported12 of 12
20085,016Not reported12 of 12
20099,999Not reported12 of 12
20107,06533.6%12 of 12
20116,53431.1%12 of 12
20128,23339.1%12 of 12
20139,20143.8%12 of 12
201410,37449.3%12 of 12
20156,91032.9%12 of 12
20168,55740.6%12 of 12
20176,53931.1%12 of 12
20188,08038.4%12 of 12
20198,40840.0%12 of 12
20208,54640.5%12 of 12
20218,17838.9%12 of 12
20226,35730.2%12 of 12
20234,40621.0%12 of 12
20246,14029.1%12 of 12
20253,49416.6%12 of 12
2026 (provisional, partial year)2,79122.9%7 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN2Conventional Hydroelectric0.8September 1988
GEN3Conventional Hydroelectric0.8September 1988

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Metropolitan Sewerage District as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Metropolitan Sewerage District and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Metropolitan Sewerage District

Questions about Metropolitan Sewerage District

How much power does Metropolitan Sewerage District produce?

Metropolitan Sewerage District reported 3,494 MWh (3.49 GWh) of net generation in 2025, a 16.6% capacity factor on 1.6 MW of nameplate capacity. From January to July 2026 it reported 2.79 GWh, which is provisional.

Where is Metropolitan Sewerage District?

Metropolitan Sewerage District is in Buncombe County, North Carolina, at 35.6497, −82.5992. It is in the Duke Energy Progress East balancing area (CPLE).

Who operates Metropolitan Sewerage District?

EIA-860M for August 2026 lists Metropolitan Sewerage District as the operator (EIA operator ID 12374). The operator is not always the owner.

When did Metropolitan Sewerage District start operating?

Its first generator began operating in September 1988, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page