Key facts

Capacity
60.4 MWNameplate
Generators
2 operatingEIA-860M, August 2026
Operating since
April 1961First generator online
Operator
Inland Paperboard - Rome MillEIA operator ID 23632
Grid
SOCOBalancing authority SOCO
Price nodes
None linkedNo verified ISO node
Location
Floyd County, GA34.2528, −85.3275
EIA plant ID
10426EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Inland Paperboard Packaging Rome produces

Free · EIA-923

Net generation, 2025

403 GWh

402,627 MWh, final

Capacity factor, 2025

65.3%

2024: 62.2%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

324.3–427.1

GWh a year. Low 2020, high 2015

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000411,763Not reported12 of 12
2001411,119Not reported12 of 12
2002397,827Not reported12 of 12
2003406,318Not reported11 of 12
2004173,996Not reported7 of 12
2005370,047Not reported12 of 12
2006331,452Not reported9 of 12
2007433,493Not reported12 of 12
200858,082Not reported12 of 12
2009401,833Not reported12 of 12
2010436,14270.7%12 of 12
2011448,14372.7%12 of 12
2012431,58469.8%12 of 12
2013386,59662.7%12 of 12
2014435,94870.7%12 of 12
2015427,07069.3%12 of 12
2016410,76366.4%12 of 12
2017415,16267.3%12 of 12
2018386,08162.6%12 of 12
2019393,83463.9%12 of 12
2020324,28052.4%12 of 12
2021424,88168.9%12 of 12
2022416,001Not reported12 of 12
2023358,025Not reported12 of 12
2024384,59762.2%12 of 12
2025402,62765.3%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN4Wood/Wood Waste Biomass22.0April 1961
GEN5Wood/Wood Waste Biomass38.4April 1989

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Inland Paperboard - Rome Mill as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Modeled

Generation potential vs reported

Monthly potential at seasonal net capability, next to EIA-923 output. Shows how much of the plant's capability was used.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Inland Paperboard Packaging Rome and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Inland Paperboard Packaging Rome

Questions about Inland Paperboard Packaging Rome

How much power does Inland Paperboard Packaging Rome produce?

Inland Paperboard Packaging Rome reported 402,627 MWh (403 GWh) of net generation in 2025, a 65.3% capacity factor on 60.4 MW of nameplate capacity.

Where is Inland Paperboard Packaging Rome?

Inland Paperboard Packaging Rome is in Floyd County, Georgia, at 34.2528, −85.3275. It is in the Southern Company Services, Inc. - Trans balancing area (SOCO).

Who operates Inland Paperboard Packaging Rome?

EIA-860M for August 2026 lists Inland Paperboard - Rome Mill as the operator (EIA operator ID 23632). The operator is not always the owner.

When did Inland Paperboard Packaging Rome start operating?

Its first generator began operating in April 1961, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page