Key facts

Capacity
2 MWNameplate
Generators
1 operatingEIA-860M, August 2026
Operating since
December 1989First generator online
Operator
Central Rivers Power US, LLCEIA operator ID 64078
Grid
DUKBalancing authority DUK
Price nodes
None linkedNo verified ISO node
Location
Anderson County, SC34.6424, −82.4544
EIA plant ID
10799EIA plant page

Data as of EIA-860M August 2026 (published 2026-09-24). Capacity is nameplate, not live output.

How much power Pelzer Upper produces

Free · EIA-923

Net generation, 2025

3.84 GWh

3,843 MWh, final

Capacity factor, 2025

21.9%

2024: 26.6%

January to July 2026

Not reported

Provisional. 0 of 7 months reported

Range, 2015 to 2025

3.8–10.2

GWh a year. Low 2025, high 2018

Annual net generation, GWhCapacity factor below each year
Annual net generation from EIA-923
YearNet generation, MWhCapacity factorMonths reported
2000Not reportedNot reported0 of 12
20013,083Not reported12 of 12
20024,285Not reported12 of 12
20038,388Not reported12 of 12
20046,975Not reported12 of 12
20057,598Not reported12 of 12
20065,000Not reported12 of 12
200720Not reported12 of 12
20084Not reported12 of 12
20095,764Not reported12 of 12
20106,52837.3%12 of 12
20116,06034.6%12 of 12
20126,98439.8%12 of 12
201314,04580.2%12 of 12
201411,33564.7%12 of 12
20158,76250.0%12 of 12
20165,99534.1%12 of 12
20175,46631.2%12 of 12
201810,22958.4%12 of 12
20195,72432.7%12 of 12
20205,81533.1%12 of 12
20214,01322.9%12 of 12
20224,49825.7%12 of 12
20234,60626.3%12 of 12
20244,67926.6%12 of 12
20253,84321.9%12 of 12
2026 (provisional, partial year)Not reportedNot reported0 of 7

* 2026 covers January to July and is provisional. Capacity factor is net generation divided by nameplate capacity times the hours of each reported month.

Power prices and basis

Free account

No verified ISO price node is linked to this plant, or its price history could not load.

Emissions

Free · EPA CAMPD

No EPA emissions units are linked to this plant.

Water use

Free · EIA-923 cooling, USGS

No EIA cooling-water record for this plant in 2024. Plants without steam cooling, such as wind, solar and batteries, do not report cooling water.

Generators

Free · EIA-860M
GeneratorTechnologyNameplate MWOnline since
GEN1Conventional Hydroelectric2.0December 1989

Ownership and offtake

Pro
Pro

Ownership and offtake are part of Pro

Owners and their shares, parent companies, and power purchase agreements with their buyers. EIA-860M lists Central Rivers Power US, LLC as the operator, which is not always the owner.

Modeled data

Pro

Pro adds modeled values for this plant. Everything above stays free.

Analyst and MCP

300 analyst questions a month, plus MCP

Query Pelzer Upper and 14,224 other projects from Claude or your own tools. Free accounts get 1 question a day.

Power plants near Pelzer Upper

More plants operated by Central Rivers Power US, LLC

Questions about Pelzer Upper

How much power does Pelzer Upper produce?

Pelzer Upper reported 3,843 MWh (3.84 GWh) of net generation in 2025, a 21.9% capacity factor on 2 MW of nameplate capacity.

Where is Pelzer Upper?

Pelzer Upper is in Anderson County, South Carolina, at 34.6424, −82.4544. It is in the Duke Energy Carolinas balancing area (DUK).

Who operates Pelzer Upper?

EIA-860M for August 2026 lists Central Rivers Power US, LLC as the operator (EIA operator ID 64078). The operator is not always the owner.

When did Pelzer Upper start operating?

Its first generator began operating in December 1989, according to EIA-860M.

Sources

  • EIA-860 2025 (final) and EIA-860M August 2026: plant, generators, capacity, operator and location
  • EIA-923 monthly net generation, 2000 to July 2026 (2026 provisional)
  • Plant names from OpenStreetMap, © OpenStreetMap contributors (ODbL)

Page updated 2026-10-04 from the InfraMap data build. Methodology · Data sources · EIA plant page